PODGORCA AIRPORT RECONSTRUCTION PROJECT. THE NEW APPROACH FOR APRON DRAINAGE SYSTEM. Scheme of a new drainage system. Duration in min. Rain intensity. ATKINS. AEROINZENEJRING. l/s/ha. mm/h. l/s/ha. mm/h. 5. 361. 130. 267. 96. 6. 330. 118. 7. 300. 108. 8. 280. 100. 9.
E N D
PODGORCA AIRPORT RECONSTRUCTION PROJECT THE NEW APPROACH FOR APRON DRAINAGE SYSTEM
Duration in min Rain intensity ATKINS AEROINZENEJRING l/s/ha mm/h l/s/ha mm/h 5 361 130 267 96 6 330 118 7 300 108 8 280 100 9 265 95 10 251 90 250 90 20 196 70.5 30 158 57 Rainfall intensity and durationfor return period of 2 years
HYDROGRAPH FOR RAIN DURATION 5 minIN LEFT OIL SEPARATOR Q=20 l/s
HYDROGRAPH FOR RAIN DURATION OF 7 min IN THE LEFT OIL SEPARATOR Q=20 l/s
HYDROGRAPH FOR RAIN DURATION OF 10 min IN THE LEFT OIL SEPARATOR Q=20 l/s
VOLUME OF RUNNOF IN OIL SEPARATOR FOR RAINFALL DURATION OF 10 MIN MAX VOLUMEDURATION OF FIRST FLUSH (POLLUTED) OF APPR 6 MIN 0.49 m3/s The first wave of polluted water Retention volume to stop first wave app 80 m3
Longitudinal section of detention pond of80m3, oil separator 20 l/s and by-pass
Plan view of detention pond of 80m3, oil separator 20 l/s and by-pass - left system
HYDROGRAPH FOR RAIN DURATION OF 7 minIN THE RIGHT SYSTEM OIL SEPARATOR Q=20 l/s
HYDROGRAPH FOR RAIN DURATION OF 10 minIN THE RIGHT SYSTEM OIL SEPARATOR Q=20 l/s
HYDROGRAPH FOR RAIN DURATION OF 5 minIN THE RIGHT SYSTEM OIL SEPARATOR Q=20 l/s
VOLUME OD RUNNOFF VOLUME IN THE RIGHT SYSTEM OIL SEPARATOR FOR RAIN DURATION OF 10 MIN AND 260m3, DURATION OF FIRST FLUSH OF APPR 6 MIN ANDVOLUME OF THE FIRST FLUSH OF 78m3 0.45 m3/s
CONCLUSION • Proposed solution of the oil separator installation to be just above the ground instead of large excavation and 5 m depth of covering. • Easier approach for oil suction and also silt disposal. • Negligible higher expenses due to energy consumption for pollution water pumping.