An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PODGORCA AIRPORT RECONSTRUCTION PROJECT THE NEW APPROACH FOR APRON DRAINAGE SYSTEM

  2. Scheme of a new drainage system

  3. Duration in min Rain intensity ATKINS AEROINZENEJRING l/s/ha mm/h l/s/ha mm/h 5 361 130 267 96 6 330 118 7 300 108 8 280 100 9 265 95 10 251 90 250 90 20 196 70.5 30 158 57 Rainfall intensity and durationfor return period of 2 years

  4. Scheme for left side drainage system

  5. HYDROGRAPH FOR RAIN DURATION 5 minIN LEFT OIL SEPARATOR Q=20 l/s

  6. HYDROGRAPH FOR RAIN DURATION OF 7 min IN THE LEFT OIL SEPARATOR Q=20 l/s

  7. HYDROGRAPH FOR RAIN DURATION OF 10 min IN THE LEFT OIL SEPARATOR Q=20 l/s

  8. VOLUME OF RUNNOF IN OIL SEPARATOR FOR RAINFALL DURATION OF 10 MIN MAX VOLUMEDURATION OF FIRST FLUSH (POLLUTED) OF APPR 6 MIN 0.49 m3/s The first wave of polluted water Retention volume to stop first wave app 80 m3

  9. Longitudinal section of detention pond of80m3, oil separator 20 l/s and by-pass

  10. Plan view of detention pond of 80m3, oil separator 20 l/s and by-pass - left system

  11. Scheme for the right side drainage system

  12. HYDROGRAPH FOR RAIN DURATION OF 7 minIN THE RIGHT SYSTEM OIL SEPARATOR Q=20 l/s

  13. HYDROGRAPH FOR RAIN DURATION OF 10 minIN THE RIGHT SYSTEM OIL SEPARATOR Q=20 l/s

  14. HYDROGRAPH FOR RAIN DURATION OF 5 minIN THE RIGHT SYSTEM OIL SEPARATOR Q=20 l/s

  15. VOLUME OD RUNNOFF VOLUME IN THE RIGHT SYSTEM OIL SEPARATOR FOR RAIN DURATION OF 10 MIN AND 260m3, DURATION OF FIRST FLUSH OF APPR 6 MIN ANDVOLUME OF THE FIRST FLUSH OF 78m3 0.45 m3/s

  16. COMPARATION

  17. CONCLUSION • Proposed solution of the oil separator installation to be just above the ground instead of large excavation and 5 m depth of covering. • Easier approach for oil suction and also silt disposal. • Negligible higher expenses due to energy consumption for pollution water pumping.