1 / 12

Washington Avenue Reconstruction Project

Washington Avenue Reconstruction Project. Public Informational Meeting. City of Chelsea. May 31, 2011. Why Project is Occurring. Poor Roadway Conditions Separation of Sewer and Stormwater Replacement of Water Replacement of Gas (by National Grid). What Does the Project Entail?.

malina
Download Presentation

Washington Avenue Reconstruction Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Washington Avenue Reconstruction Project Public Informational Meeting City of Chelsea May 31, 2011

  2. Why Project is Occurring Poor Roadway Conditions Separation of Sewer and Stormwater Replacement of Water Replacement of Gas (by National Grid)

  3. What Does the Project Entail? • Project Details • Geographic Scope of the Work • Heard St to Route 16 • Back of Sidewalk to Back of Sidewalk • Reconfiguration of Cary Square • Full-Depth Roadway Reconstruction Explanation • New Street Surface • New Sidewalks • Streetscape Amenities (Benches, Bike Racks, Trees, Etc.)

  4. What Does the Project Entail? • Funding Sources • Municipal Borrowings through General Obligation • Sewer and Water Bonds • Chapter 90 Funds • Community Development Block Grant Funding • MWRA Grant and Zero Interest Loans • Total of $6M+

  5. What Does the Project Entail? • Project Construction Schedule • Water, Sanitary & Drain - Spring/Summer/Fall 2011 • Streetscape – Spring/Summer/Fall 2012 • Completion – Spring 2013

  6. Project Schedule • Contract has been awarded to J. Marchese and Sons • Work starts Monday June 6th • Work hours approximately 7 AM to 3:30 PM, Monday through Friday

  7. Construction Schedule

  8. Construction Schedule

  9. June Construction

  10. July Construction

  11. August Construction

  12. Questions/Comments/Concerns?