300 likes | 331 Views
Learn about the revised project scope for the Guilderland School District capital construction plan, including cost adjustments and deferments. Stay informed on the timeline and upcoming meetings.
E N D
Capital Construction Project Director of Facilities Clifford Nooney
Capital Project Discussion and Approval Timeline Board Meetings February 11 – Information March 12 – Information/BOE & Community Q & A March 19 – Board Action
Facilities Committee Guiding Principles Keep all students SAFE Keep all students HEALTHY & COMFORTABLE Ensure all students are FUTURE-READY
Capital Construction Project Cost Estimated Median Homeowner Tax Impact *Note: $3,120,000 from the Capital Reserve Fund will be applied to lower the amount borrowed for the project.
Approach to Reducing the Project Scope Phase 1: Reduce costs through reengineering, redesign, or cost estimating adjustments Phase 2: Reduce costs by delaying or deferring needed work, in part or in full, into the future
Phase 1 - Cost Adjustments (-$2.5 million)The following changes to the original project scope are recommended to reduce costs through reengineering, redesign, cost estimating adjustments, or deferring improvements:
Phase 1 - Cost Adjustments (-$2.5 million) ContinuedIn addition, since the time the proposed project was recommended by the Facilities Committee in June, 2018, new facilities issues have emerged that are recommended for inclusion in the revised project scope:
Phase 2 - Project Scope Deferment (-$9.6 million) F = Full Deferment P = Partial Deferment
Capital Construction Project Cost Estimated Median Homeowner Tax Impact *Note: $3,120,000 from the Capital Reserve Fund will be applied to lower the amount borrowed for the project.