National Environmental Satellite, Data and Information Service (NESDIS)NESDIS Suomi National Polar-orbiting Partnership (NPP) Post Launch Operational Readiness George Serafino, Chief Office of Systems Development Ground Systems Division May 3, 2012
Agenda • Open Action Items • Project Summary • Issues / Risks • Significant Progress • Schedule / Milestones • Backup • Scope • Points of Contact 2
Integrated Ground System Readiness Summary for NPP NDE Segment Development (SD) Product Development (PD) Network Infrastructure (NI) ESPC Operational Readiness (OR) FEB MAR APR FEB MAR APR FEB MAR APR FEB MAR APR G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G G G G G G G G G G G G G G G Y Y G G Y G G Y Y Y Y Y R R G G G Y Y G G G G G G R R Y R R R System Integration (SI) CLASS (CL) User Engagement (UE) Calibration/Validation (CV) FEB MAR APR FEB MAR APR FEB MAR APR FEB MAR APR G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST Y Y Y G G G G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G G G G Y Y Y G G G G G G R R Y Y Y R G G G G Y Y R R R Y R R Y Y Y G Y Y R R R R R R G G G Overall NPP Readiness Assessment LEGEND Overall NPP Readiness Assessment FEB MAR APR G G G NOV DEC JAN REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST OVERALL NOT STARTED Y R Y G Y Y TECHNICAL SCHEDULE COST OVERALL GOOD SHAPE G Y Y Y Y Y Y MINOR PROBLEM Y Y Y Y G G G MAJOR PROBLEM R R R R G Y Y Y Y Y
Integrated Ground System Readiness Open Issues for NPP Project Codes UE = User Engagement SD = Segment Development NI = Network Infrastructure PD = Product Development CL = CLASS SI = System Integration CV = Calibration Validation OR = Operational Readiness 7 r = requirements s = schedule c = cost p= procurement t = technical
Integrated Ground System Readiness Open Issues for NPP Project Codes UE = User Engagement SD = Segment Development NI = Network Infrastructure PD = Product Development CL = CLASS SI = System Integration CV = Calibration Validation OR = Operational Readiness 8 r = requirements s = schedule c = cost p= procurement t = technical
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont)
Integrated Ground System Readiness Open Issues for NPP (cont) 16
Integrated Ground System Readiness Open Issues for NPP (cont) 17
Integrated Ground System Readiness Open Issues for NPP (cont) 18
Integrated Ground System Readiness Open Issues for NPP (cont) 19
Integrated Ground System Readiness Open Issues for NPP (cont) 20
Integrated Ground System Readiness Critical Milestones for NPP One More Manifest test this year remaining testing deferred until next FY
Integrated Ground System Readiness Risks for NPP L x C Trend Criticality Approach M – Mitigate W – Watch A – Accept R - Research Increasing (Worsening) Unchanged Decreasing (Improving) High Med Low
Risk Focus Chart M 24
Integrated Ground System Readiness Schedule for NPP (October 2011 – April 2013)
Integrated Ground System Readiness Schedule for NPP (October 2011 – April 2013)
Integrated Ground System Readiness Summary Status for NPP • NDE/NCEP- ATMS and CrIS radiances in BUFR format being streamed to NCEP/NCO using FTP protocol (FTP-S to be used when NCO transitions to new computer system in September 2013) • NDE continues to conduct data streaming exercises/tests w/AWIPS and NWSTG as part of a Phase 2 testing event. ~14 orbits (24hrs) of priority 1 products transferred • Status of NDE documents to support external user tests: • NDE to NWSTG/AWIPS Test Plan: Updated to reflect Phase 2 Tests. NDE is in the process of seeking AWIPS and NWSTG signatures (for Test Plan acceptance) • NDE to NWSTG/AWIPS Phase 2 Procedure Document: In final stages of development • NDE/AWIPS/NWSTG Phase 2 Test Report: Being generated • NDE to CLASS Test Plan: Signed/Complete • NDE/CLASS Test 2 Procedure Document: Finalized/Ready for Test 2
Integrated Ground System Readiness Summary Status for NPP (cont) • User Engagement • OSD continues to regularly meet with user groups to review short- and long-term data requirements • Initial and end-state data product lists and volumes determined and documented for all NWS NCEP centers, AWIPS, CLASS, STAR, SAB, & NIC; Initial EUMETSAT products determined. Lists updated continuously as new data becomes available • STAR personnel actively engaging ocean color community on characteristics and utility of VIIRS imagery and products • System Development • NDE contractor presented Build Content Review for User Services and Monitoring & Reporting on 12/13/2011; Government approved proceeding with SW development. • Funding for second production string identified and allocated in FY12
Integrated Ground System Readiness Summary Status for NPP (cont) • Network Infrastructure • NDE/AWIPS - Network components (for testing) in-place and configured. Continue to support ongoing NDE External testing • NDE/NCEP – 10 Gbps connectivity established to NCEP Central Operations (NCO) in Gaithersburg, MD via NCEP Point of Presence (POP) at NSOF • NDE/CLASS - Test 1 completed successfully 3/20/2012 using FTPS connection (InitialFunctionality/Interface Test) • NWAVE connection between CLASS/NSOF and NCDC operational • EUMETSAT: • EUMETSAT is scheduled to upgrade TAT T-1 link (into POES SOCC) to a new 10Mbps circuit by April 2012. EUMETSAT will provide an installation schedule for the upgrade of the TAT T-1 link (into POES SOCC) to a new 10Mbps circuit after contract issued, probably in May 2012. • New circuit is then scheduled to be upgraded to 50Mbps in the second quarter of 2013. This link will then work in tandem with the IJPS DS-3 link and combine and back up most existing data flows and carry NPP data between EUMETSAT and NOAA (EARS T-1 circuit will remain). NOAA part of project on hold until end of 2012 • EUMETSAT planning up upgrading their servers at NOAA as part of network wide tech refresh. Schedule TBD
Integrated Ground System Readiness Summary Status for NPP (cont) • CLASS • NPP xDRs from IDPS routinely flowing to CLASS • CLASS-STAR connectivity established at NSOF for timely delivery of NPP xDRs to STAR for cal/val purposes • System Integration • NDE production environment equipment on order and arriving at NSOF as of April 2012 • NDE contractor schedule for integration of production environment into ESPC extended to November/December 2012 time frame • Products will continue to be generated and distributed to users using NDE system test environment until production environment is ready • Product Development • FY12 funding shortfall of $1.2M poses risk to continuity of existing polar products • As of April 12, awaiting decision from JPSS on covering of shortfall
Integrated Ground System Readiness Summary Status for NPP (cont) • Calibration / Validation • ATMS and CrIS Sensor Data Records appear to be of excellent quality (Provisional? Beta?) • VIIRS still degrading but rate of degradation appears to be slowing; data still within 50% margin as of early April 2012 • Most STAR SDR/EDR SOWs for assessing quality of IDPS algorithms have been approved for funding by JPSS; 3 SOWS out of 20 remain unfunded as of April 5, 2012 • STAR working closely with GRAVITE teams to streamline algorithm change processes • Operational Readiness • Transition to Operations Plan completed and approved by OSPO • Implementation of LAN upgrade behind schedule due to delay in procurement funding by JPSS; completion of LAN upgrade and testing anticipated by end of June/early July 2012 time frame • Funding for ESPC operations staffing did not materialize in FY12, resulting in possible delays of NDE transition to operations
Upcoming Events • NDE-AWIPS/NWSTG Phase 2 Testing (Functionality Testing): Mar April 2012 (occurring now) • NDE Operational Readiness Review (ORR) – Apr 2012 May/June TBD • NDE-EUMETSAT Testing (Functionality/Performance): April/May 2012 (Occurring now)