1 / 10

THIRD PARTY INSPECTION BY QUALITY SUPERVISION CONSULTANTS

THIRD PARTY INSPECTION BY QUALITY SUPERVISION CONSULTANTS. G.C. Tallur (Former Secretary, PWD) Advisor, IDS Cell Tuesday, July 12, 2005. Third Party Inspection of Works, Goods & Equipments Current Status - Works.

gleaton
Download Presentation

THIRD PARTY INSPECTION BY QUALITY SUPERVISION CONSULTANTS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THIRD PARTY INSPECTION BY QUALITY SUPERVISION CONSULTANTS G.C. Tallur(Former Secretary, PWD)Advisor, IDS Cell Tuesday, July 12, 2005 Advisor, IDS Cell

  2. Third Party Inspection of Works, Goods & EquipmentsCurrent Status - Works • There are no specific provisions regarding inspection of works in the Karnataka PWD Code • Clause 12(b), 12(c) & 13(a) of PWG 65 currently govern execution of works to the required quality • Contractor is primarily responsible for quality • Executive Engineer / Assistant Executive Engineer are engaged in multifarious activities, administrative, financial, technical & hence cannot bestow unstinted attention to quality of works. • They are responsible for progress & also quality. This is a conflict of interest. Advisor, IDS Cell

  3. Current Quality Control Set up - Works • QC set up is inadequate • QC staff are, by & large, disgruntled or dissatisfied • QC staff function under officers in-charge of execution of works. • QC staff are drawn from the same organization & inter-transferable. • Poor quality works are numerous & result in poor return for investment. • Contractors do not engage any technical staff though required to do so. • In-house QC is hence in a poor shape. Advisor, IDS Cell

  4. Current QC status - Goods • SPD-now closed, did not have its own inspection wing. It depended on Departmental Government officers. • KPTCL specifies that materials during manufacture & thereafter are to be tested by the manufacturer / supplier in the presence of KPTCL engineer. • Both lack modern professional element. • While the present system of inspection for works / goods / equipment can be acceptable for small value works / goods, a better system is needed for larger ones. Advisor, IDS Cell

  5. Independent (Third Party) Inspection Agency Advantages: • They are professionally qualified • They have necessary experience. • They are independent • They are not responsible for targets, progress, payment etc & hence there is no clash of interest. • This will ensure value for money • This will check corruption • This will stop low quality work getting accepted & paid for as is likely to happen now. • G.O. No. FD 55 Pro.Cell 2004, dated 17-02-2005 providing for Third Party Inspection already issued. Advisor, IDS Cell

  6. The Provisions of G.O No. FD 55 Pro.Cell 2004, dated 17-02-2005 • Third Party Inspectors (TPI) (Quality Supervision Consultants) (QSC) to be appointed to improve quality of works / goods / equipments. • TPI mandatory for all works contracts of estimated value > Rs. 2 crores & all goods / equipments contracts of value > Rs. 25 lakshs. • QSC to be appointed as per the G.O PWD 121 SO/FC 2003, dated 26-09-2003 for appointment of Consultants. Advisor, IDS Cell

  7. Employment of QSC • Well defined TOR to be drafted to engage QSC • Detailed checklists to be completed by QSC to be prepared (with the assistance of experts if need be) to ensure satisfactory performance by QSC. • QSC can be engaged for one or more works / supply of goods / equipments or for a specified term for a Procurement Entity. • HOD / MDs of PSUs / Boards / Societies / Local Bodies to engage QSC & order their payment on satisfactory performance. • Expenditure on QSC to be charged to the relevant work / procurement estimates. Advisor, IDS Cell

  8. QSC inspections • QSC to inspect works periodically • QSC to submit reports as per checklists to the Employer / copy to the Secretary / Managing Director • QSC to inspect goods / equipments during manufacture / before dispatch / after receipt, assembly & commissioning. • Engaging QSC does not absolve the primary responsibility of the Employers towards sound quality of works / goods / equipments. • QSC are there to assist the Employer / purchaser in discharging their primary responsibilities. • QSC not to be engaged where a specialized in-house QC organization exists or a separate Supervision Consultant has been already engaged. Advisor, IDS Cell

  9. KTPP Act & TPI • Applicable to all Procurement Entities as defined in Section 2(d) of Chapter-1 • This G.O about engaging TPI / QSC to be included in the special conditions of Contract of the Tender documents. • The Contents of this G.O will be incorporated in the Karnataka PWD Code & other manuals. Advisor, IDS Cell

  10. THANK YOU Advisor, IDS Cell

More Related