380 likes | 392 Views
Update from ERCOT Retail Market Services to RMS March 4, 2003. Retail Market Update. Topics GISB 1.4 Update Texas Set Version 1.5 Market Participant Testing Flight Test V1.5 Overview ERCOT Data Transparency Move-In/Move-Out Task Force.
E N D
Update from ERCOT Retail Market Services to RMS March 4, 2003
Retail Market Update Topics • GISB 1.4 Update • Texas Set Version 1.5 • Market Participant Testing Flight Test V1.5 Overview • ERCOT Data Transparency • Move-In/Move-Out Task Force
Data Transport in the Texas MarketGISB 1.4 UpdateRMS Meeting 2/25/03
Review of Transport Options • FTP - Currently primary option for all MPs to ERCOT • No guaranteed delivery, some security concerns • HTTPS – ERCOT replacement for FTP • Guaranteed delivery, improved security • GISB 1.4 – Primary option for MPs on point to point • Guaranteed delivery, same security issues as FTP • GISB 1.6 – Primary transport for 2004 Texas market • Guaranteed delivery and improved security
ERCOT Testing/Migration Team • ERCOT team working closely with MPs on connectivity and GISB 1.4 EDM testing • Testing schedules and issues being addressed at Texas Data Transport Working Group based on market rules • ERCOT Team includes: • Clay Katskee – Connectivity Test Coordinator - Primary • Nagaraju (Naga) Valasagandla – Secondary • Dave Farley – Project Manager (IT)
GISB EDM 1.4 Migration Status • Testing with Market Participants In Progress • 7 MPs have completed testing with no issues • 30 MPs have completed testing with issues identified • 6 MPs are in process of testing with issues • 1 MP testing delayed due to architecture issue • Issues Impacting MP Testing include: • Improper use of MP log on and password • File naming conventions not followed • Use of non unique file names
Next Steps • Migration to production will be coordinated with individual MPs after successful completion of testing • ERCOT is working with the MPs and TDTWG to identify and resolve issues • ERCOT may not be able to resolve issues that are contrary to market rules or those that compromise system performance and proper market reporting • MPs that cannot complete testing can stay with FTP until GISB 1.6 can be implemented or test the HTTPS solution for data transport
Texas Set V.1.5 Presented by: Dave Odle Tuesday, February 25th, 2003
V1.5 Coordination Team Accomplishments/Goals • V1.5 Coordination Team – Task Complete • V1.5 Team face to face meetings are completed. • Original TASKS conceived when team was created in May, 2001: • Increase Communication in the market for V1.5 - Tremendous improvement and continuing • Establish Market Project Timeline and plan - Complete • Establish clear understanding of V1.5 requirements - Complete • Numerous accomplishments • Created the V1.5 website for transparency and open communication. • Created the Version 1.5 mailbox for more discreet issue resolution. • Created some extremely helpful documentation for everyone's use (thanks to all who did this). • Worked through difficult and convoluted requirements and reached resolution on all of them. • Worked through all V1.5 requirements (change controls), one by one, for clear understanding and expectation. • Created the project timeline and critical milestone dates (flight testing, migration, etc.) • Created the production implementation plan down to the last conference call. • Pointed out the "what if's" and identified risk mitigation methods. • Continuing efforts for Project Success –In Progress • Continue Efforts in open communication • Project Status and tracking • Production Migration coordination • Flight Test coordination with the TTPT and ERCOT
Project Status Summary • Exolink provides EDI services for: Republic, Calpine, Entergy Retail, Entergy Disco, GEXA • Systrendsprovides EDI services for: Sheryland, Tenaska, Occidental, TCE • EC Power provides EDI services for: AEP A-REP, SmartEnergy, Just Energy • ESG provides EDI service provider for: ACN Energy, Cirro Group, Coral Energy Markets, Dynegy, Sempra Energy Solutions, Tractebel Energy Markets, UBS Warburg, Tara Energy
ERCOT Reliant Energy Retail TXU ES Logica Simplified Nueces San Patricio Constellation Entergy Retail AEP TDSP DESIGN Green Mountain 25% 50% 75% EC Power BUILD INTERNAL TEST 25% 50% 75% STEC Retail ESG AEP A-Rep Sharyland Systrends TCE Tenaska/Occidental ONCOR ASP ES = Flight Test Frame 1 Exolink TNMP (TDSP) Certain Power (POLR) First Choice Power Republic XERS (Xcel Energy) Center Point Spark Energy LP Utility Choice Electric Project Status Summaryas of 2/20/03
Implementation Plan • Objectives • Ensure all parties know the status of the implementation effort AT ALL TIMES! • Minimize down time • Work as a team
Initiating Transactions Shut-down Timeline 6 hrs 6 hrs 14 hrs Step 1 Step 3 Step 4 Step 2b CR ERCOT TDSP ERCOT CR Step 2a Step 5 9 pm 3 am 1 am 7 am 7 am 9 pm Noon Thursday, April 10th Friday, April 11th
Sub-Initiating Transactions Shut-down timeline 6 hrs 6 hrs 8 hrs Step 1 Step 2b Step 3 Step 4 CR ERCOT TDSP ERCOT CR Step 2a 11 am 5 pm 9 pm 3 am 3 am 11 am Friday, April 11th Thursday, April 10th
Legend = Conference Calls CRs ERCOT TDSPs Implementation Shutdown Overview Wednesday Midnight Thursday Noon Thursday Midnight Friday Noon Friday Midnight 814_01, 814_10, 814_16, 814_24 1 am 6 hrs 14 hrs 6 hrs 9 hrs 814_08, 814_12, 814_18, 814_20, 814_26 9 pm 6 hrs 8 hrs 6 hrs 6 hrs 867 2 pm 8 hrs 7 hrs 810 5 pm 1 hr • 650 Initiating will cease on Friday at 2 pm, 650 Responses will cease on Friday at 6 pm • 814_PC will cease on Friday at 5 pm, 814_PD will cease Friday at 6 pm
Conference Call Schedule during Migration • Wednesday @ 5 PM • Initiating Transaction status/ CR processing status • Thursday @ 9 AM • Initiating transactions completed/ERCOT confirms 1 AM cut-off/TDSP & CR processing health and status. • Friday @ 9 AM • Sub-initiating transaction processing/ERCOT confirms Thursday 9 PM cut-off/TDSP & CR processing health and status. • Friday @ 5 PM • TDSP & CR to confirm 650, 810, & 814 PtP cut-offs and processing/ERCOT to provide 867 processing status • Saturday @ 9 AM • ERCOT & TDSP to report status of Migration • Saturday @ 7 PM • ERCOT declares (if possible) “go/no-go”/TDSP & CR to report status • Sunday @ 9 AM • TDSP & CR provide status of migration/ERCOT fall back for declaration of “go/no go” • Sunday @ 3 PM • ERCOT provides time it will begin accepting V1.5 transactions/TDSP & CR provide status- decision of having another conference call.
Next Steps • Meetings for this team have concluded. Our next conference call will be held on March 18th with the Flight Test Administrator and the TTPT to establish Flight Test status. • March 18th (Tuesday) – Conference Call. Follow up meeting will be scheduled post April 11th for a lessons learned analysis.
Flight V1.5 Overview • Goal of testing: To ensure Market Processes are successfully tested according to testing criteria, procedures established by TTPT, ERCOT and market protocols • After completion of flight test, TTPT will have ‘Lessons Learned’ session to address issues brought up during pre-flight and flight testing.
Flight Test Responsibilities Activities and responsible Parties • Pre-Testing Activities and Parties responsible - ERCOT, PUCT, TTPT • Daily Flight Activities and Parties responsible - ERCOT, MPs, TTPT Scheduled Activities and Test Schedule • Pre-Testing Activities – 10/25/02 – 2/24/03 • Daily Flight Activities – 2/24/03 – 4/17/03 • Certification Activities - begin upon completion of the v1.5 Flight
Frame 1 Readiness – End to End & ETOD • TTPT meeting held in Houston on 2/19, the team discussed the readiness for Frame 1 testing to begin Monday, February 24. Recommendations as follows: • End to End Script Testing - TTPT and Flight Administrator recommend that End to End Script Testing Frame 1 begin on schedule on Friday, February 24. • ETOD Script Testing - TTPT and Flight Administrator recommend that ETOD Script Testing Frame 1 begin on March 3 (delay of 1 week).
Frame 1 ETOD scripts TDSPs who use ETOD: • TNMP - ok with recommendation • Entergy - ok with recommendation • Sharyland - ok with recommendation • It is expected that due to the nature of ETOD script testing, as a market, we can advance the frames for ETOD script testing faster in order to catch up with the frames for End to End script testing and not cause an overall delay for the flight test. • Update 3/3: Starting ETOD scripts Tuesday, March 4
Frame 1 End to End Scripts - Progress Frame 1 Status: • 30/43 CRs were complete with Frame 1 (sending/receiving) as of Friday 2/28 • 10 more CRs were complete with sending, were still confirming receipt of inbound as of Friday 2/28 • 3 CRs still had Frame 1 transactions to send as of Friday 2/28. • ERCOT rejected back transactions to some CRs and requested CRs to resubmit corrected transactions (Sat/Sun/Mon) • ERCOT working with all TDSPs to identify outstanding transactions expected to receive in Frame 1 and communicate back any resends required to the CRs
Frame 1 End to End Scripts - Progress Frame 1 Status – continued • Problem uncovered with how TDSPs and ERCOT executed 2 scripts (SC345, SC349). ERCOT and TDSPs working to get files to run. • One TDSP has to receive all 814_03s before they can run an extra billing cycle in order for a future frame 6 transactions to process correctly. This process will take 3 days to execute. • Market has not moved to Frame 2
Flight V1.5 – Test Timeline • Existing Market Participants - 6 week process defined • New Market Participants - 8 week process as defined • Muni-Coop Participants – 8 week process as defined • CRs testing in Additional TDSP territories – 8 week process as defined • CRs testing in MCTDSP service territories – 8 week process as defined
Flight V1.5 - Notes • Reminder – the market flight test progresses as fast as the slowest participant. • Flight Administrator (Karen Bergman) will work closely with all market participants to assist and keep all market participants on the proposed schedule. • Proposed schedule is one frame per week. • ERCOT testing team includes 11 people to assist in the day to day management of testing. • Team assignments have been communicated to market participants from the Flight Administrator.
ERCOT Data Transparency • ETS / GISB (PR# 30136) • All code changes have been made within ETS • Files have been changed within GISB and FTP to account for ETS requirements, including additional timestamp information • Unit Acceptance Testing completed February 21, 2003 • Scheduled implementation date February 26, 2003 • ETS / TX Set 1.5 (PR# 20060) • Preliminary analysis of required changes completed on February 14, 2003 • Work is progressing on Design and Migration documentation • Testing and implementation will coincide with TX Set 1.5 project
ERCOT Data Transparency • Performance Measures (PUC# 20124) • Preliminary analysis completed on February 21, 2003 • Determination was made to use ETS as data source • Project request is being written for approval • Manual report generation to be done for Q1 PUC reports • Automated reporting should be available for Q2 PUC reports • ERCOT Data Transparency(PR# 30054) • Further analysis required as a result of SCR727 implementation
RMS Update on Move-In / Move-Out Task Force February 25, 2003
Solution to Stacking Background on NFI rejects • Existing Market Design • Current market design does not support multiple non-sequential transactions on an ESI ID. • Volumes encountered • February 1st through 20th – 3.2% (300 per day) • Safety – Net Manual workarounds • Relieves the effects to the customer from NFI rejects. • Causes out-of-sync system conditions. • Causes higher costs and higher potential for mistakes. • Increases quantity of orphan accounts. (increase of UFE) • Requires backdated transactions, which causes additional NFIs, out-of-sync conditions, and more manual workarounds for the TDSPs. • Same CR point-to-point initiatives • Relieves the effects to the customer from NFI rejects for those transactions. • Requires that the TDSPs handle multiple non-sequential transactions. • Causes out-of-sync conditions if TDSP is not handling multiple non-sequential transactions.
Solution to Stacking Study Approach • Other market designs • ERCOT ‘Mother ship’ concept • JIT (Just in Time) • Centralized scheduling with delayed notification to ERCOT • Changes to existing design • Building the ability to handle multiple non-sequential transactions within the current market structure. • Cost and schedule restraints of all market participants
Solution to Stacking Proposed Design • A method that allows CRs, ERCOT, and TDSPs to accept (and process) multiple, non-sequential transactions concurrently on a single ESI ID. • Requires new business rules to sequence multiple transactions. • May require system changes for all market participants • Benefits expected • Significant reduction in NFI rejects • Significant reduction in need for Safety Net Move-Ins • Better manages customer expectations (Dates, billing, etc.) • Fewer backdated clean up efforts • Fewer Cancel/Re-bills • Helps keep systems in sync • Reduces UFE • Reduces transaction volume • Expedites connecting and billing the customers by the correct CR • Improves transaction reliability
Solution to Stacking Next Steps • Establish high-level design • Cost benefit analysis
Timelines for approved concepts • ERCOT Monitoring • Cancelled with Exception • Implemented 1/9/2003 • Rejects • In Analysis • Date Reasonableness • 12/19/2002 implemented • Pending 814_06s • 2/9/2003 ERCOT implemented temporary fix • 3/1/2003 ERCOT system impact analysis due for permanent fix • Implementation projected for early June • Retired ESI Ids • Version 1.6 • Invalid ESI ID retry • 3/1/2003 ERCOT system impact analysis due • Implementation projected for early June • De-Energize flag (ignore CSA) on Move-Outs • 3/1/2003 ERCOT system impact analysis due • Implementation projected for early June • ESI ID Start/Eligibility Date • 3/1/2003 ERCOT system impact analysis due • Implementation projected for early June
Invalid ESI ID Rejects • Approved by RMS on October 16th • Expediting ESI ID Creates - A report by TDSP by percent of Invalid ESI ID reject to total 814_16 transactions will be made available to RMS prior to each RMS meeting for an undetermined period of time. The report will encompass a two-week time frame as close as possible to the RMS meeting (not too far in the past). This report will be provided by ERCOT • January 3rd through February 20th Total 814_16sPercent Invalid ESI ID • AEP 49803 3.73% • Centerpoint 92835 1.12% • Oncor 122241 5.24% • Sharyland 247 12.55% • TNMP 8573 1.18% • 2 TDSPs showing improvement from last period