120 likes | 283 Views
INNOVATIVE AUTOMATION OF ELECTRICAL DESIGN OF OFF-SHORE WINDFARMS TO FIND THE LEAST COST OPTION. Infrastructure & Cities Sector, Smart Grid Division Siemens Power Technologies International (PTI) Presenter:Victor Sellwood Dr. Dusko P. Nedic (dusko.nedic@siemens.com)
E N D
INNOVATIVE AUTOMATION OF ELECTRICAL DESIGN OF OFF-SHORE WINDFARMS TO FIND THE LEAST COST OPTION Infrastructure & Cities Sector, Smart Grid Division Siemens Power Technologies International (PTI) Presenter:Victor Sellwood Dr. Dusko P. Nedic (dusko.nedic@siemens.com) Victor Sellwood(victor.sellwood@siemens.com)
Presentation Overview • Introduction - why Optimise construction and operation costs? • Development and Experiences / Validation of a software tool for automating the electrical design of large off-shore wind farms. • Case Study 1 - Edge-located collector platforms vs Central-located • Case Study 2 - Comparison of CAPEX / OPEX for offshore windfarms based on publicly-available data • Conclusions
Why Optimise Construction / Operation Costs ? • UK's Round 3 program will offer 32.2GW / 36GW and there is up-to 80GW offshore in the North Sea • 2010: National Grid announced that a radial offshore transmission network is not acceptable • 2011: Ofgem report shows that moving from an Independent (radial) to Integrated (mesh) transmission system could reduce Capex from £18B to £15.4B (-16%) • A study showed that for only 2 wind farms in the North Sea considering only voltage as a choice, design options would exceed 7,000 • Image from “Eirgrid_Offshore_Grid_Study_FA Nov2011.pdf”
Software Tool for automated design Tool Features: • Three analysis sub-systems • Inter-array cable system • Off-shore platforms • Off-shore transmission • Automated design of inter-array cable system and VUI for correcting such designs. • Catalogue of components. • Creating of network models and possibility of merging them. • Cable sizing. • Voltage/reactive power control. • Electrical losses. • Reliability. • CAPEX and OPEX evaluation.
Interactive tool for creating/editing inter-array cable system. Multiple projects. Restructure string, change string origin, shift platform, swap strings between platforms Find and correct cable crossovers Information on the selected project Adding/editing cable knee points Visualisation User Interface (for modifications of inter-array cable design)
Proving the Software Tool by Practical Application Driven by projects / clients and cooperation with the UK Universities • HornSea (over 10 different transmission options with sensitivity analyses) • Seagreen (4 different transmission options and a number of sensitivity analyses) • UoM Electrical Engineering – research project and a PhD to assess thousands of electrical designs for different offshore wind farm sizes • University of Strathclyde – Industry supervision of a 4 year PhD on transmission options in North-Sea. The research will be conducted using the tool. • Dogger Bank - Inter array cable design (over 80 layouts – capacity ranging from 7GW to 20 GW) • Availability calculations: • London Array • Greater Gabbard
Case Study 1: Comparison of Edge- vs Central- location Centrally Located option (CLo) Edge Mounted option (EMo) Each platform 600 MW, 18 strings per platform (14 of 5WTGs strings and 4 of 4WTG strings).
Case Study 2: Illustrative Comparison of Design Options Based on Publicly-Available Data Investment Cost in £ (Millions) Cost figures for illustrative purposes only!
Case Study 2: Illustrative Comparison of Design Options Based on Publicly Available Data • Case 1 and Case 3 use the same electrical components -> losses are same • Case 2 has least electrical losses as no HVDC conversion equipment and good reliability because of the 3 x HVAC shore connections • Case 3 has least reliability losses due to redundant string connections • Case 4 has most electrical losses as longest string cables, but the least Investment Cost as the quantity of higher gauge cables is less • This demonstrates that the differences in Investment are swamped by the differences in Costs of Losses during operation
Conclusions • This automated approach significantly reduces the time for manual and visual inspection / verification of the proposed cabling system for the layouts • Risk of human errors is significantly reduced and re-verifications / inspections can be quick and efficient • Effortlessly and quickly design and undertake cost benefit analyses of preferred options. • Possibility to merge network models for cost benefit analyses of the off-shore grid. • Complex design solutions can easily be compared (both construction and operation) using the most significant comparator: cost