Phase I Decommissioning Project Update

Phase I Decommissioning Project Update. West Valley Demonstration Project. Presented by: Bryan Bower, Department of Energy November 14, 2012. High Level Waste Canister Relocation and Storage Project. Current Activities: Reviewed Concrete Storage Cask fabrication activities at Zion (CHBWV)

gwoodberry
Download Presentation

Phase I Decommissioning Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Phase I Decommissioning Project Update West Valley Demonstration Project Presented by: Bryan Bower, Department of Energy November 14, 2012

  2. High Level Waste Canister Relocation and Storage Project • Current Activities: • Reviewed Concrete Storage Cask fabrication activities at Zion (CHBWV) • NAC prepared the project plan (NAC) • Design for Storage System - Due December 31, 2012 (NAC) • Design for Storage Pad (NAC) – January 30, 2013 • Design for transport system (NAC) – Dec 31, 2012 • Request For Proposal for decontamination canisters (CHBWV) – December 2012 NAC Project using Vertical Storage

  3. MPPB Accomplishments • Continued pre-demolition activity in the Lower Extraction Aisle and Chemical Operating Aisle for systems disposition • Continued asbestos abatement in Cold Lab of the Analytical Aisle • Continued characterization of high hazardous areas Drilling Tell-Tale in LXA/COA Draining Piping in LXA/COA 3

  4. Vitrification Facility Accomplishments • Completed air gap of Vitrification Off-Gas piping between trench and 01-14 Building, including grout bulkhead • Removed components containing hazardous constituents from Vit Facility Aisles (e.g., circuit boards, lamps, batteries) – formerly used for treatment Vit Off-Gas Pipe Air Gap in Trench Haz. Component Removal in Vit 4

  5. 01-14 Building Accomplishments • Completed electrical and mechanical isolations and air gap to facility • Completed removal of shielded pipe chase • Shut down facility blowers and stack monitoring • Completed Off-Gas and main plenum filter removal • Prepared for demolition Shielded Pipe Chase Cutting Shieled Pipe Chase Air Gap 5

  6. 01-14 Building: Demolition Phases After Step 1 Original Construction After Step 2 6

  7. Balance of Site Facilities Accomplishments Completed demolition of: • Maintenance Storage Area • Product Storage Area • Old Warehouse and Counting Lab Slabs • Vehicle Repair Shop • Vitrification Test Facility Waste Area Slab • Vitrification Construction Fab Shop Slab • Waste Tank Farm Test Tower Vit Fab Shop Slab Demo Waste Tank Farm Test Tower Vehicle Repair Shop Demo 7

  8. Waste Shipping Accomplishments • Completed5 of 12 low level waste (LLW) and 2 of 4 mixed low level waste (MLLW) interim shipping milestones • Total volume of legacy waste shipped since contract start: • 44,335 ft3 versus plan of 41,951 ft3 of legacy LLW • Exceeds FY2012 plan 6 months ahead of schedule • 1,607 ft3 of legacy MLLW • 120 ft3 of legacy hazardous and universal waste (Completed) • 814 ft3 of legacy industrial waste Loading LLW shipment in LSA 4 LSA 4 TRU and LLW container storage 8

  9. Waste Shipping Accomplishments • Total volume of newly generated (NG) waste shipped since contract start: • 3,696 ft3 of NG LLW • 110 ft3 of NG MLLW • 204 ft3 of NG Hazardous and Universal waste • 10,185 ft3 of NG Industrial waste Waste Load Out of the Old Warehouse Pad 9

  10. Questions? 10