LEGEND. Completed Work in Progress Tender Stage. GNSS PROJECT (PHASE-I). SARVARAJA SAGAR (3.059 TMC). VAMIKONDA SAGAR (3.249 TMC). POTHIREDDYPADU HEAD REGULATOR Sill : +841’. BANAKACHERLA CROSS REGULATOR. Tunnel 5.25 Km. OWK RESERVOIR 4.31TMC. GANDIKOTA RESERVOIR
E N D
LEGEND Completed Work in Progress Tender Stage GNSS PROJECT (PHASE-I) SARVARAJA SAGAR (3.059 TMC) VAMIKONDA SAGAR (3.249 TMC) POTHIREDDYPADU HEAD REGULATOR Sill : +841’ BANAKACHERLA CROSS REGULATOR Tunnel 5.25 Km OWK RESERVOIR 4.31TMC GANDIKOTA RESERVOIR FRL + 209 M CAP: 11.943 TMC(Live) 16.840 TMC (Gross) KM 24.33 PKG 47 PKG 49 PKG 48 SRMC SRBC Bypass canal (5 M dia) KM 32.64 SRBC 57.700 KM 16.225 KM 56.775 KM KM 16.50 KM 34.80 KM 52.875 PKG 1 PKG 2 KM 0.00 GNSS Flood Flow Canal GNSS FFC PKG 89 GORAKALLU RESERVIOR Capacity: 10.29 TMC FRL : +261 M Package: Open Category With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I.
GALERU NAGARI SUJALA SRAVANTHI Name of the Contractor : M/s MAYTAS-NCC (JV), Hyd. Agreement Amount : Rs. 250.20 Crs. Agreement Date : 25-10-2004 Period of Completion : 30 Months Target date of Completion : 4/2007 • Package No.1 [EPC System] • Construction of Gandikota dam across Penna river. • Earth work excavation of main canal from Km. 0.000 to Km.24.330, fabrication and erection of radial crest gates, stop log gates and its accessories, river sluice gates, gantry crane etc. • Construction of Head Regulator. • Investigation : Completed • Design (Canal) : 12 Km length approved against 24.33 Kms. Completed • Execution (Canal): 12 Km length completed against 24.33 Kms. • Execution (Dam): Exploring drilling completed. • Qty. of earth work done : 52,93,972 cum against 81,98,000 cum • Qty. of concrete work done : 2,807 cum against 3,04,000 cum • Expenditure :Rs. 78.21 Crs. (Inc. Mob. Adv. Rs. 12.51 Crs.) against Rs. 250.20 Crs. • 2004-05 : Rs. 12.51 Crores (mob. Adv. Only) • 2005-06 : Rs. 65.7 Crores. • Land Acquisition :Required 16397 Ac. Acquired 3398 Ac. Requisitioned:16398 Acs • R & R : Estimate under preparation
GALERU NAGARI SUJALA SRAVANTHI • Package No. 2 • Excavation of main canal from Km. 24.33 to Km. 32.64. • Formation of Vamikonda Sagar and Sarvaraya Sagar reservoir and leading channels to reservoirs and its distributaries etc. Name of the Contractor : M/s Gammon India Ltd., Mumbai Agreement Amount : Rs. 294.45 Crs. Agreement Date : 25-10-2004 Period of Completion : 30 Months Target date of completion : 4/2007 • Investigation : Completed • Design : 5 Km length approved against 10 Km • Structures : Under Approval • Execution : 6.5 Km length in progress against 10 Km • Qty. of earth work done : 6 T cum against 7.73 T cum • Expenditure :Rs. 43.78 Crs. (inc. mob. adv. Rs. 14.72 Crs) against Rs. 394.45 Crs. • 2004-05 : Rs. 14.72 Crs. (Mob. Adv.) • 2005-06 : Rs. 29.06 Crs. • Land Acquisition :Required – 5253 Ac. Requisitioned : 5053 Acres Acquired : 419 Acres. • R & R : Estimate under preparation
GALERU NAGARI SUJALA SRAVANTHI • Package No.47 / Cat – II • Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of Head Regulator from Km.0.000 to Km. 16.500.. Name of the Contractor : Engineers & Contractors, Hyd. Agreement Amount : Rs. 72.99 Crs. Agreement Date : 28-2-2005 Period of Completion : 24 Months Target date of completion : 2/2007
GALERU NAGARI SUJALA SRAVANTHI Name of the Contractor : Coramandal Prestcerte(P)Ltd, Hyd. Agreement Amount : Rs. 78.55 Crs. Agreement Date : 28-2-2005 Period of Completion : 24 Months Target date of Completion: 2/2007 • Package No.48 / Cat – II • Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD works from Km.16.500 to Km. 34.800.
GALERU NAGARI SUJALA SRAVANTHI • Package No.49 / Cat – II • Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD works from Km.34.800 to Km. 52.300. Name of Contractor : Coramandal Prestcerte (P)Ltd Agreement Amount : Rs. 73.658 Crs. Agreement Date : 28-2-2005 Period of Completion : 24 Months Target date of Completion: 2/2007