An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Percival Landing Update Land Use Committee Meeting March 27, 2014 City of Olympia | Capital of Washington State

  2. History Percival Landing Update

  3. Approach • GOAL • Protect public safety • Maintain use by the public • Plan for the future • INSPECTION PROGRAM • Initial assessment by structural engineers in 2004 • Annual walk-through inspections • Regular 5-year structural inspection – next scheduled for 2014 • ANNUAL CFP • Percival Landing Inspections funded through CAMMP • Percival Landing Major Maintenance funded through CAMMP • Percival Landing Replacement Projects Percival Landing Update

  4. Summary of Actions Percival Landing Update

  5. Previous Percival Landing Funding • 2011 CFP • Section A Phase 1 Construction - $150,000 • Section A Phase 2 Design - $350,000 (Moved to cover additional contamination costs) • Annual inspection - $8,000 (CAMMP) • Percival Landing Maintenance Fund - $25,000 (CAMMP) • 2012 CFP • Annual inspection - $6,500 (CAMMP) • Percival Landing Maintenance Fund - $50,000 (CAMMP) • 2013 CFP • F Float Replacement - $297,000 • Annual inspection - $6,800 (CAMMP) • 2014 CFP • 5-year inspection - $43,000 (CAMMP) • Percival Landing Maintenance Fund - $27,000 (CAMMP) Percival Landing Update

  6. Projected Costs and Timeline • Section A Phase II • Repair boardwalk $750,000 within 3-4 years • Replace floats $6.5M • Replace all $15M • Section B • Repair boardwalk$1.6M within 3-4 years • Replace $20M • Section C • Repair boardwalk$1.3M within 5-10 years • Replace $20M Percival Landing Update

  7. F Float Replacement • Background • Closed F float in January 2013 • Designed and bid replacement project. • Received bids December 5, 2013. • Bids received exceeded funds available. • Permit timeline limitations • Single float manufacturer willing to bid • Currently reviewing options for moving forward Percival Landing Update

  8. Options • Option A) • Rebid as designed. This would require the allocation of an additional $440,000. • Option B) • Obtain a second engineering opinion or evaluation. • Option C) • Change design to fit within remaining funds ($400,000). Project would include: • Removal of all of existing F Float • Construct only the pump out finger float as designed • Install new pump out • Repair F Float as originally designed (flotation and structural) • Add water and power to existing E Float Percival Landing Update

  9. Option C) E & F Float Proposal F Dock: Replace single float for new pump out F Dock: Remove moorage floats E Dock: Add water and power Percival Landing Update