150 likes | 303 Views
MPSC Procedures An update. Alick Macpherson Rutgers University/ETH Zurich. MPSC Procedures: Observations. Purpose: Procedures are required for systems that can by their malfunctioning cause significant damage to LHC equipment Procedures are required for 3 types of system:
E N D
MPSC ProceduresAn update Alick Macpherson Rutgers University/ETH Zurich
MPSC Procedures: Observations • Purpose: Procedures are required for systems that can by their malfunctioning cause significant damage to LHC equipment • Procedures are required for 3 types of system: • Central system: This is the BIS. • Standard System: A system that interfaces only to the BIS • Complex System: • A system supplies inputs to systems in addition to the BIS. • A system that reacts to signal from the BIS (ie BEAM_INFO, SAFE_Machine parameters) • Examples • Central: BIS • Standard: PIC, WIC, FMCM • Complex: Vacuum, BLM, LBDS • Systems not (yet) included in the MPSC procedures • Electron stoppers (RF), Access, Movable objects + … A. Macpherson: MPSCWG - Procedures
MPSC Procedures: Status A. Macpherson: MPSCWG - Procedures
Timetable for Completion of Procedures • All out-standing procedures submitted to Jan by 1st October*. • Procedures returned to groups after review/cross check by Jan/Alick • Expect ~ 1 week per procedure for review and feedback and 2 weeks for corrections. • Target: Review 1 procedure per week. • Review process started with BIS procedure • From 1st October, start EDMS checking procedures • Tareget: 1 per week. • Start with BIS procedure • As EDMS approval finishes, transfer to MTF. • Allow 1 week for transfer to MTF • Look to have all procedures in MTF by mid December * Collimator procedure linked to presentation at MPSCWG on 3rd Oct A. Macpherson: MPSCWG - Procedures
Procedures: More Observations • Most procedures have had a first revision • Still awaiting some procedures • Question: is data/state logging considered part of MPS commissioning? • MPSC Commissioning should (where possible) be modular • Use hardware commissioning to set entry conditions for front end systems. • HWC Procedures + results (MTF) to be confirmed by MPSC procedure • Test the interface with the BIS => complementary to BIS Commissioning • Set exit conditions that allow the system to proceed to validations during cold machine cold checkout or validation with beam. • MPSC validation must insure that there is no possibility of machine protection risks due to operator controls • => procedures to confirm that operators can’t change critical settings? • Dependency on info from BIS and other systems must be made clear A. Macpherson: MPSCWG - Procedures
Procedures: Flag concerns BEAM_INFO Flag • BEAM_INFO is a mirror of the BEAM_PERMIT that is returned to the systems inputting to the BIC • Questions: • Does the system initiate protective actions based on feedback from the BIS • Does the system use the BEAM_INFO flag for critical actions • If BEAM_INFO= FALSE is used, what are the timescales of the actions? • Can systems ensure that the initiation of any protective action is > 3 orbits • Assumption: need a max of 3 orbits to trigger and dump beams Safe Machine Parameters: Understand if/how they are used • Questions: • Is toggling of USER_PERMIT conditional on the state of the SAFE BEAM flag • If this happens, is the logic integrated into the CIBU/BIC or the user system • Does any subsystem use SAFE_INJECTION flag as part of MPSC • Does any subsystem use Movable_devices_allowed flag as part of MPSC A. Macpherson: MPSCWG - Procedures
Observations: Vacuum System Vacuum system: good example of movable objects • Interlock Chain: includes sector valves, electron stoppers, Access Safety Block • Need to confirm commissioning of redundant interlocking mechanisms • ie vacuum + access, vacuum +RF? • Need to commission joint system configuration • RF commissioning mode: ie sector valves open, electron stoppers closed • Need to confirm protection from equipment failure of movable devices • Access Safety Block • Vacuum system provides signals directly to others: RF, MKI, MKB, Access • Concerns: are dump requests compatible with MPSC • Initiation of RF dump requests on loss of good vacuum on P1 cavity. • RF Dump request mechanism depends on intensity threshold + single/multiple cavity loss. • MKI: Vacuum signals used to assert injection inhibit. Can initiate valve closure. • MKB: Kicker interlock based on vacuum system can generate a dump request • Access system: Ensure that the control logic and configuration for the electron stoppers and Access Safety Block are such that there is redundancy in the interlocking • Uses BEAM_INFO =FALSE as a necessary condition for closing sector valves • In failure mode, what are the sufficient conditions (eg leak detection) A. Macpherson: MPSCWG - Procedures
Observations: PICs and WICs • Entry Conditions: • Front end commissioned in HWC • Need to re-confirm procedures and MTF results from HWC • Focus on PIC–BIS and WIC–BIS validation • PIC and WIC treats both beams simultaneously • Dump request applies to both beams simultaneously • PIC specific features • PIC does not use USER_PERMIT_A and USER_PERMIT_B • Uses unmaskable and maskable USER_PERMIT instead • Timescale Concern: • Is system reaction to fault detection (BEAM_INFO=FALSE) too fast for completion of beam dump. Essential Circuit fault detection: ~ few s • SAFE BEAM Flag and Auxiliary circuits • Need to confirm location of interlock truth table for Auxiliary circuit faults + SAFE_BEAM • WIC specific features • Timescale concern: • Is system reaction to fault detection (BEAM_INFO=FALSE) too fast for completion of beam dump. Fault detection for Fast Boolean Processor of WIC: ~ 1 s A. Macpherson: MPSCWG - Procedures
Observations: BIS • Procedure almost ready for checking via EDMS. • Validation of subsystem interface with BIS requires: • Valid USER_PERMITs (or reasonable USER PERMIT simulator?) • Clear statement of subsystem functionality wrt BIS • BIS logic • Clarification that all logic for setting BEAM_PERMIT to FALSE is within the BIS system • Confirm there is no safe machine parameter dependence attached to the USER_PERMIT. • USER_PERMIT as received by the BIS: Clarify difference between “A AND B FALSE” and “A OR B FALSE” when setting the BEAM_PERMIT (during commissioning) • Timing issues: • Validation of worst case time from user system toggling the USER PERMIT to completion of a beam dump= > confirm fastest reaction timescale A. Macpherson: MPSCWG - Procedures
Observations: FMCM • Entry conditions established by HWC • Commissioning in situ and with pilot beam • Beam time at 450 GeV and 7TeV beam is needed to set trigger thresholds and trigger time-window • FMCM inputs only into the BIS • Inputs are maskable • Special commissioning mode • FMCM test mode: can set USER_PERMIT FALSE on request • Need to confirm this mode cannot be invoked during running • Data logging essential • used to set trigger threshold for USER_PERMIT • Included in MPSC procedure A. Macpherson: MPSCWG - Procedures
Observations: LBDS • For MPSC, LBDS is a complex system: • Beam dump related Inputs • BEAM PERMIT loop trigger from BIS • Direct TCDQ BLM trigger (independent of BIS) • Direct Access system trigger (independent of BIS) • Interlock related Outputs • LBDS USER_PERMIT • Can LBDS set its USER_PERMIT to FALSE with beam in the machine? • Injection Inhibits sent to injection kickers and re-phased RF revolution frequency sent to abort gap watchdog • Commissioning needs to be cleanly divided into • Individual User system tests, Hardware Commissioning, and MPSC tests. • MPSC entry conditions must confirm previous test sets • Use MPSC tests to validate chain of control prior to the LBDS Reliability Run • detailed 1st draft but …needs more focus on MPSC for a non-ideal situation. • Address issues and modes of (partial) failure of component user systems • Implications of lost abort gap synchronisation from the RF • Partial loss of communication with injection system • Define acceptance criteria/functionality for tests so to permit clear validation. • How does the procedure adapt when the criteria are not quite met. • Clarify implications of LBDS internal dump requests A. Macpherson: MPSCWG - Procedures
Summary • Procedures • 1st drafts of available procedures have been reviewed. • Will circulate back to subsystems for corrections and cross checks. • Need to get all out-standing 1st drafts • Submit revised procedures for EDMS approval then to MTF • Start process now and finish by mid December. • Global picture • Assess interdependencies between systems in relation to MPSC • Clarify if any automated actions are based on feedback from the BIS • If so, ensure timescales are compatible with integrated system response • Require procedures confirm no operations influence on critical settings • Address MPSC risks for partial failure modes, especially in complex systems like the LBDS • Understand/review implications to protection given different states of the safe machine parameters ( SAFE_BEAM, SAFE_INJECTION etc) • Ensure that any safe machine parameter dependent interlock logic is in BIS A. Macpherson: MPSCWG - Procedures
Spare Stuff A. Macpherson: MPSCWG - Procedures
Access Safety Block • Covered by both Access and Vacuum system interlocks • Time scale for closure is slow (~ 3sec) => much slower than beam dump. A. Macpherson: MPSCWG - Procedures