The LHC Beam Dumping System. The LHC Beam Dumping System V.Kain, R. Suykerbuyk Input from: E. Carlier, B. Goddard. Contents: LHC Extraction in LSS6 – LHC Beam Dumping System (LBDS) Equipment, Interfaces, Software Testing – Reliability tests, Scenario tests Summary.
E N D
The LHC Beam Dumping System The LHC Beam Dumping System V.Kain, R. Suykerbuyk Input from: E. Carlier, B. Goddard • Contents: • LHC Extraction in LSS6 – LHC Beam Dumping System (LBDS) • Equipment, Interfaces, Software • Testing – Reliability tests, Scenario tests • Summary 08Nov07
LHC Extraction in LSS6 – LHB Beam Dump System (LBDS) • Fast extraction (kicker and septa) • Dilution • Beam dump • Protection Dump block Dilutionkickers Extraction septum Diluter block Extraction kickers 08Nov07
LBDS Beam Instrumentation • Additional beam instrumentation, shown for one beam • BLMs missing…(32 per beam, 2 special ones on TCDQ) 08Nov07
LBDS Interfaces FMCM Interfaces: triggering, synchronisation, energy tracking, arming, BIS, injection BIS 08Nov07
LBDS Software No mention of the internal LBDS controls software (slow control software, fast acquisition, synchronisation unit, …). • “LBDS Monitoring GUI” ← does not exist yet, no person assigned (maybe Eric) • like WinCC • shows alarms • IPOC results • shows status of different sub-systems • shows status of BETS • can be used to re-arm LBDS • XPOC 08Nov07
LBDS software – XPOC (1) • LSA software • External Post Operational Check after EACH beam dump • LBDS safety critical • analysis of last beam dump to verify that worked correctly • IPOC (beam dump hardware) + BI + … • even if postmortem event suppressed, XPOC carried out • XPOC analysis could cover enough even for “bad programmed dump” (no PM event) • ‘Operational state’ of beam dump depends on XPOC result • analysis specified not to take longer than 5 s • XPOC triggered on ‘beam dump’ event • XPOC on server. Data collection and analysis start automatically. • event generated by timing as soon as permit loop broken • during analysis beam permit removed via SIS • SDDS file structure in event trees • results are written to file in event tree • XPOC GUI: browser, model builder, view analysis results • XPOC references MCS settings • List: LHC-TD-ES-0001 08Nov07
LBDS software – XPOC (2) 08Nov07
LBDS software – XPOC (3) • XPOC Status • analysis packages so far only for • BTVDD traces • MKD waveforms • MKB waveforms • signals not written to event tree file structure yet • no GUI with browser yet • no references in LSA yet 08Nov07
LBDS - Controls Requirements (1) • “No” LSA settings – LBDS core is hardcoded • But: • Q4 currents, discussion: critical settings • MSD currents, discussion: cirtical settings • TCDQ functions • Only command: ARM (before first injection) • Logging • to be defined • e.g. BETS logged with 1 Hz, during pulse higher frequency • Fixdisplays • to be defined • BTVDD, BLMs in extraction region, BPMSE update each dump …N2 pressure at TDE continuous update,… • MCS • XPOC references • BETS look-up tables: MKD/MKB strengths vs. energy, Q4/MSD current vs. energy, DCCTs vs. energy, … • Q4, MSD current? • Alarms • to be defined for operations. Alarms on FESA level defined → WINCC • OASIS • idea for the time being: 1+15 MKD kicker waveform, revolution frequency, circulating beam signal • Maybe not required: IPOC FESA class preapres everything digitally • TCDQ: collimator control 08Nov07
LBDS - Controls Requirements (2) • Applications for BI: • BTVs: application of Fabio • BPMs: BPMD in a separate FESA class • BPMD probably only for XPOC • Interlocked BPMs? • Probably YASP, critical settings, like CNGS • (fast position interlock for later on) • BLMs: normal ones in dump line? • Special ones on TCDQ? • FBCTs: application of Markus 08Nov07
LBDS - Controls Requirements- Sequencer • Has to arm the LBDS (+ BIS) • via LBDS FESA device • Has to manage the OPERATIONAL STATES of the LBDS. • depend on XPOC results, access in LSS6 • e.g. LBDS available for operation without beam/ pilot at 450 GeV • Provokes programmed dumps • depending on operational scenario: • unlink/link permit loops via BIC FESA class • prepare timing tables with events to: • dump beam • post mortem suppression/re-enable • For inject & dump, circulate & dump, injection intermediate, single beam MD • Set # turns on turn counter value at inject & dump LBDS hardware 08Nov07
Other stuff • Access procedures? • Padlock dump caverns during run? • During shutdown needs to be accessed for maintenance of BTVDD electronics, radiation monitors, water pump • FMCM on MSD • Supervision application ready 08Nov07
Testing… (1) • As LBDS is safety critical a RELIABILITY TEST is planned • Two phases: • ‘stand-alone’ reliability test • 10 weeks during hardware commissioning • ‘fully-connected’ reliability test • 450 GeV ‘fully-connected’: 2 weeks, during machine check-out • 7 TeV ‘fully-connected’: 4 weeks, during machine check-out • Documentation will be in MTF • A lot of open issues…parallelism? Availability of closed BIS loop,… • As soon as possible from CCC – running already in local • would need: • timing: XPOC triggering • sequencer – arming, timing 08Nov07
Testing…(2) 08Nov07
Reliability Testing (1) • ‘Stand-alone’ (10 weeks) – during hardware commissioning • NEEDS LOGGING CONFIGURED • NEEDS XPOC (to some extent) • (NEED IPOC) • Fake DCCT signals from MBs, Q4 and MSD to BEM/BETS from local FGCs • is there • No connection to access system • Fake RF signal from local FGC (for RF revolution frequency signal) • is there • BIS needed: if loop not closed yet, close locally • The arrival of the signals from DCCTs, access system,… have to be tested independently of the stand-alone reliability test during the hardware commissioning, also: • FMCM on MSD • MSD software interlocked? BETS tracking…. • TCDQ functions • IPOC fully tested after this phase 08Nov07
Reliability Testing (2) • ‘Fully-connected’ – during check-out • 450 GeV (2 weeks) • allows beam operation at 450 GeV, pilot • Connection to LHC access system: the LHC needs to be CLOSED!! • TCDQ direct link BLMs • SLP distribution to be tested • Links to MKIs to be tested • Real DCCTs from MBs, MSD, Q4. • RF • BIS. Loop closed • Operational: MKD, MKB, MSD, Q4, BIS, TDE, Vac, TCDQ, TCS, BI, DCCTs, RF ref. freq. signal • LHC cycling • 7 TeV (4 weeks) • allows beam operation up to 7 TeV, pilot • XPOC will only be fully commissioned after first experience with beam 08Nov07
Scenario Testing • We should foresee “scenario tests” • Emergency beam dump: permit loops are linked, PM not suppressed • USER_PERMIT change • Both permit loops broken • LBDS triggers both dumps • CTG detects open loop, sends beam dump event (XPOC) and PM event • XPOC • PM buffers frozen by PM event • PM data pushed to server • Programmed dump at end of fill: permit loops linked, PM not suppressed • Timing table executed containing events dump beam 1 and dump beam 2 • Removes CTG user permit • … • Dump only one beam at end of fill, need to suppress PM event for this beam • Inject & dump: • Injection warning, suppress beam 1 PM (with correct delay), dump beam 1 in timing table • Inject and dump hardware: set with the correct delay turns • Suppress the PM event for one beam, unlink permit loops • Inject and dump hardware counts number of turns and then removes user permit • .. • After dump re-arm BIS and LBDS • … 08Nov07
Summary • LBDS equipment – installation – hardware commissioning: • Work in progress • Settings into LSA, XPOC, applications: • Most of it defined, people assigned • “LBDS Monitoring GUI” not assigned yet • Testing… • Big issue – parallelism,… • Need to discuss also “partial testing” for “Sector test” , etc. • Very much work in progress 08Nov07