Bitter Creek Stream Restoration. Preliminary Engineering Report Neighborhood Meeting. Project Orientation. WILLIAM CANNON. BRANCHWOOD. BITTER CREEK. RIPPLE RUN. BUCKS RUN. Meeting Agenda. Introductions Creek History Current Conditions & Proposed Solutions Question & Answer.
E N D
Bitter Creek Stream Restoration Preliminary Engineering Report Neighborhood Meeting
Project Orientation WILLIAM CANNON BRANCHWOOD BITTER CREEK RIPPLE RUN BUCKS RUN
Meeting Agenda • Introductions • Creek History • Current Conditions & Proposed Solutions • Question & Answer
Introductions • Project Sponsor, Watershed Protection Department • Janna Renfro • (512) 974-3422 • janna.renfro@austintexas.gov • Design Engineers, CH2M Hill • Heather Harris • (512) 249-3327 • heather.harris@ch2m.com • Neighbors • Name • Location
Project Areas (New Survey) = 311 Erosion Complaints 3 1 2 BITTER CREEK RALEIGH CIR BRANCHWOOD BUCKS RUN
Project Area 1 @ BRANCHWOOD DRIVE • Cover channel to… • Discourage dumping • Join stormdrains • Improve safety • Increase connectivity
Project Area 1 • 30’ Drainage Easement • Threatened property • Safety concerns • Steep & eroding banks • Minimal natural function • Incised channel
Project Area 1 • Recommended Solution • Raise Channel Bed (3 – 6 ft) • Tiered Channel • 2 ft pilot channel • 4 ft floodplain bench • 8 ft total depth • Vegetated Banks • Rock Bottom • Continuous over ~600 ft Existing 30’ Easement
Project Areas = 311 Erosion Complaints 3 1 2 BITTER CREEK RALEIGH CIR BRANCHWOOD BUCKS RUN
Transition 2 1 Similar Project • Recommended Solution • Grade Control Structure(s) to make elevation change Similar Project
Project Area 2 • Wider channel • Wider easements • Some stable areas • Isolated severe erosion spots
Project Area 2 • Too wide • Deflections • Debris • Trash • Invasive vegetation
Project Area 2 • Recommended Solution • Clean up channel • Provide defined flow path • Passive restoration • Improve quality of vegetation
Project Area 2 Bank erosion on Area 2 • Recommended Solution • Spot fixes for severely eroded banks Similar Project
Project Area 2 Side gully on Area 2 • Recommended Solution • Spot fixes for side gully formations Similar Project
Project Area 2 Outfall Erosion on Area 2 Similar Project • Recommended Solution • Spot fixes for failing and eroded outfalls
Project Area 2 • Recommended Solution • Assess condition of existing projects
Project Areas = 311 Erosion Complaints 3 1 2 BITTER CREEK RALEIGH CIR BRANCHWOOD BUCKS RUN
Project Area 3 • Recommended Solution • Evaluate improvements to enhance water quality downstream
Project Areas 1 Continuous, Engineered & Vegetated Channel 2 Clean-up, Spot fixes, & Passive Restoration 3 3 Pond Improvements for Water Quality 1 2 BITTER CREEK RALEIGH CIR BRANCHWOOD BUCKS RUN