190 likes | 352 Views
Gordon Comegys SRWG Chair. SRWG Status Report January 24 , 2013 Las Vegas, NV. SRWG Products For TSS Approval. DPM Revisions Study Program Procedure document 2012 Study Program Report. DPM Revisions. Add guidance for including sub 100kV elements Clarified generator netting threshold
E N D
Gordon ComegysSRWG Chair SRWG Status Report January 24, 2013 Las Vegas, NV
SRWG Products For TSS Approval • DPM Revisions • Study Program Procedure document • 2012 Study Program Report
DPM Revisions • Add guidance for including sub 100kV elements • Clarified generator netting threshold • Link to Area Coordinator list in definition • Clarified Planned Facilities definition • Assigned bus number range for BCCS multi-section line dummy buses • Alternative version adds Line Long Identifier field requirement for data to simulate Category B’s (withdrawn by MSRATF) • Confirmed DPM satisfies standards • Except this uncertainty in MOD 11: R1.1. Bus (substation): name, nominal voltage, electrical demand supplied (consistent with the aggregated and dispersed substation demand data supplied per Reliability Standards MOD-016-0, MOD-017-0, and MOD-020-0), and location.
Study Program Procedure document • Instructions from TSS for SRWG to finish drafting for TSS January approval • Web conference on Oct 9 revised draft • Incorporate PCC member comments • Final document approved at Nov SRWG meeting Motion To Approve
2012 Study Program Report • Focus area- Idaho/Montana/Northwest • Colstrip ATR model • COLATR model couldn’t find elements directed to trip • Manually identified and included in switching sequences • Trip times from contingency data owners • Recommend process to develop approved model
2012 Study Program Report (continued) • Data errors for 12 gen units • Units swing out when adjacent units stable
2012 Study Program Report (continued) • Gen unit issues forwarded to MVWG Power Plant Modeling Task Force • No Performance Log Items • Change to Posted Report (suggest by Tom Green) I have a minor comment to the first bullet in the Executive Summary. If possible, could we consider changing the language from: “Assess system performance by simulating probable high-impact disturbances” to something like: “Assess system performance by simulating disturbances with a potentially high impact to the system” I think the way it’s written implies that the disturbances are probable. Thanks, Tom
TSS Action Item to SRWG for Gen Baseload Flag • 13HS2 Approved Case with Baseload Flag=2 • 47% of Pmax in case have BL flag=2 regardless of status • 124326 MW out of 264665 MW Pmax • 47.5% of Pmax in case have BL flag=2 for status on • 100203 MW out of 210857 MW Pmax • 45% of Pmax with status off and BL flag=2 • 24123 MW out of 53807 MW
SRWG Actions • Added to Representation Log • Use of dynamic models not on approved list (replace “Generator w/o dyn model” column with “dyn model not approved”) • Missing or invalid Load Long_ID’s • NEW> Create Table of Case Metrics • Intent: give feedback to data submitters • Count of unknown generator turbine types (type 0 in required turbine type field) • Use of non-conforming load flag compared with Load Long_ID’s identifying industrial and station service • Use of generator Q-Table (reactive capability curves)
SRWG Actions (continued) • Case Supplemental Material issued with each case • Removed the following due to lack of use • Series compensation list • Supplemental Line Flow Summary • Phase Shifting Transformers • Area Reserve Factor • Remove detailed PSS list, only retain summary • User practice is to examine the case directly and not rely on supplemental info
SRWG Actions (continued) • Meeting format change • Two sub-groups remain (Compliance and Study Program) • Previous Planning Tools sub-group activity is now a separate BCCS Assurance Team • No simultaneous sub group break out sessions tried out • Sequential sub-group discussions led by sub group chair • All participated • Future use of separate, task specific sub group web meetings • Consensus to discontinue break out sessions at SRWG meetings
Other Discussions with no action • Operating base case loads compared to actual (presented by Zach Zornes, Chelan PUD) • aggregate actuals 10% lower than base case • Production Cost Model (presented by Rich Bayless, Ron Schellberg, Gil Coulam, Steve Wallace) • Potential use of PCM generation pattern for future cases
Other Discussions with no action (continued) • Base case signoff sheet • Discussed signoff option doesn’t include disagreement with other system’s model • Problem origin: interpretation of criteria for what is to be represented in planning cases • Expected to be resolved by BCCS project classifications
Other Discussions with no action (continued) • Modeling and Validation Work Group • Summarized approved MVWG documents • Reminders to use approved dynamics models that supercede old models now not approved (SVC’s, GENTPJ, wind gen models) • Reminder to provide data for new power flow required fields for dynamic simulations (load Long_ID, Turbine Type, Baseload flag integer)
Data Request from PCC Study Program Task Force • Submittals for critical contingencies • APS 500kV Category B • Avista- eastern Washington Category B’s and C’s • Chelan- 230kV Category B • El Paso- 345kV Category B • Idaho Power- 230kV Category B • Northwestern- Colstrip generator unit tripping • Nevada- 500kV and 345kV Category B’s • PACE- 345kV Category C • PG&E- 500kV Category D’s • PNM- 345kV Category B • SCE- 500kV Category B • Tri-State/PSCO/WAPARM – 345 & 230kV Category B’s and C’s • WAPAUW- 161kV Category C
2013 SRWG Meeting and Workshops • April 10-12 - WECC Salt Lake City • July 15-16 – Bellevue, WA (PSE Hosting) • July 17 – SRWG Workshop, Bellevue,WA • July 18-19 MVWG Workshop, Bellevue,WA • Nov 12-14 – WECC Salt Lake City
SRWG Leadership Team • Gordon Comegys, present Chair • Retiring from ColumbiaGrid next week • Pamela Mclean, Vice Chair and Secretary • Will be serving as Chair effective Feb 1 until end of term in August • Don Streebel, Chair of Compliance Sub Group • John Gross, Chair of Study Program Sub Group
Gordon Comegys Email gcomegys@ieee.org Questions?