1 / 20

EEGS IRKP2 Meeting

EGNOS Extension to Eastern Europe. EEGS IRKP2 Meeting. 24 th June, 2010 Warsaw. CONTENTS. Status of GMV activities in EEGS: WP1: Project Management WP2: EGNOS Improvement in Eastern Europe WP3: Regional Feasibility and Integration Studies WP4: Demonstration Activities

hawa
Download Presentation

EEGS IRKP2 Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EGNOS Extension to Eastern Europe EEGS IRKP2 Meeting 24th June, 2010 Warsaw

  2. CONTENTS • Status of GMV activities in EEGS: • WP1: Project Management • WP2: EGNOS Improvement in Eastern Europe • WP3: Regional Feasibility and Integration Studies • WP4: Demonstration Activities • WP5: Dissemination Activities EEGS IRKP2 Meeting

  3. WP1 Project Management

  4. WP1: Project Management Activities done in the period: • Contractual management: no activities in this period. • Documentation management: IRKP2 delivery done. • Tracking of the project status to ensure timely release of deliverables: progress reports requested and provided to GSA. • Review and verification of deliverables • Organization of progress meetings and reviews (notification, agenda, chairing and reporting) • Identification of the need for interfaces with external entities: EGNOS Advisory Board. • Management of contribution and access to project information in the GSA tool GKMF (GNSS Knowledge Management Facility.): EEGS management in GKMF EEGS IRKP2 Meeting

  5. WP2: EGNOS Improvement in Eastern Europe Activities done in the period: • WP 2.1: Finished at IKRP1. • WP 2.2: Data processing improvements • WP 2.2.1: SRC-PAS performs ionosphere analyses: see SRC presentation. • WP 2.2.2: GMV has performed the analysis: see next slides. • WP 2.3: Infrastructure improvements • WP 2.3.1: ROSA provides data for additional station(s): done • WP 2.3.2: MAO provides data for additional station(s): done • WP 2.3.3: RSS provides data for additional station(s): data not needed. • WP 2.3.4: GMV perform the analysis: not started. EEGS IRKP2 Meeting

  6. WP2.2.2: Data Processing: Baseline Case New EGNOS release (V2.3.1)EEGS proposed release Max. Safety Index: 0.28 Max. Safety Index: 0.27 EEGS IRKP2 Meeting

  7. WP2.2.2: Data Processing: Degraded Case RIMS OK New EGNOS release (V2.3.1)EEGS proposed release Max. Safety Index: 0.29 Max. Safety Index: 0.29 EEGS IRKP2 Meeting

  8. WP2.2.2: Data Processing: Degraded Case RIMS Problems New EGNOS release (V2.3.1)EEGS proposed release Max. Safety Index: 0.33 Max. Safety Index: 0.33 EEGS IRKP2 Meeting

  9. WP3: Regional Feasibility and Integration Studies Activities done in the period: • WP 3.1: GNSS context, RIMS and Service Provision • WP 3.1.2/3/4: ROSA/MAO/RSS completes information: done for IRKP2 • WP 3.1.5: AENA review ROSA, MAO and RSS docs: done for IRKP2 • WP 3.1.6/7/8: ROSA/MAO/RSS implements comments: to be done for MTR • WP 3.2/3.3: EGNOS/SDCM Interoperability/PPP (see next slides) • WP 3.2.4: RSS performs studies for SDCM: done for IRKP2 • WP 3.2.5: GMV performs the studies for EGNOS: done for IRKP2 • WP 3.2.6: RSS and GMV will consolidate the information: done for IRKP2 draftly and final version for MTR • WP 3.4: Galileo Impact: done for IRKP2 in a first version. Final version for MTR. EEGS IRKP2 Meeting

  10. WP3.2: EGNOS/SDCM INTEROPERABILITY SERVICES • The study concludes that once EGNOS and SDCM will be certified, interoperability is possible (as far as the systems comply with MOPS and SARPs): • If MOPS is not updated for GLONASS, interoperability by using just the GPS corrections and integrity from SDCM. • When MOPS will be updated for GLONASS, interoperability with SDCM providing corrections and integrity for GPS + GLONASS • Interoperability can be provided in two ways: • Selection of satellites from different SBAS signals (not in Approach) • Switching between SBAS data streams coming from different SBAS signals (all modes) EEGS IRKP2 Meeting

  11. WP3.3: EGNOS/SDCM PPP SERVICES • Activities done in the period: • First version of D12 for IRKP2 finalised • Overview and brief technical description of PPP technique • Assessment of PPP performances using a global network • Sensitivity to various performance drivers (observation time, reference products) • Usage of GLONASS • Feasibility of PPP service using a regional network for product generation • EGNOS: GPS only (no GLONASS L1/L2 available) • Preliminary assessment of performances: promising results EEGS IRKP2 Meeting

  12. WP3.3: EGNOS/SDCM PPP SERVICES • PPP performances (different reference SW) EEGS IRKP2 Meeting

  13. WP3.3: EGNOS/SDCM PPP SERVICES • PPP performances (observation period) EEGS IRKP2 Meeting

  14. WP3.3: EGNOS/SDCM PPP SERVICES • PPP performances (constellation, 1h observation period) EEGS IRKP2 Meeting

  15. WP3.3: EGNOS/SDCM PPP SERVICES • Preliminary regional performances on EGNOS data • Comparison between global (IGS) and regional PPP EEGS IRKP2 Meeting

  16. WP4: Demonstration Activities Activities done in the period: • WP 4.1: Definition and Procurement • WP 4.1.2: GMV adapts magicSBAS to EDAS + Integration & RTCM convertor: done. Final tests with MAO pending. • WP 4.1.4/5/6/7: SRC/ROSA/MAO/GSY prepare the demo and fills the doc: first version of doc done for IRKP2, final version for MTR. • WP 4.1.8: GMV contributes with magicSBAS characteristics: on a per-request basis • WP 4.1.9: GMV prepares demo for Interoperability and PPP and fills doc: first version of doc done for IRKP2, final version for MTR. • WP 4.1.10: RSS prepares demo for Interoperability and PPP and fills doc: first version of doc done for IRKP2, final version for MTR. • WP 4.2: EGNOS Extension Demonstrations: to be started after MTR • WP 4.3: EGNOS/SDCM Demonstrations: to be started after MTR • WP 4.4: Results analyses: to be started after MTR EEGS IRKP2 Meeting

  17. WP4.1: EGNOS/SDCM Interoperability demonstrations • At GMV level, the GEO switching functionality will be used to make an interoperability exercise between EGNOS (GPS) and SDCM (GPS and GPS+GLONASS modes) EEGS IRKP2 Meeting

  18. WP4.1: EGNOS/SDCM PPP demonstrations • Activities done in the period: • First version of D20 for IRKP2 finalised • Regional PPP service based on EGNOS RIMS (GPS only) • Data preparation • Performance assessment criteria • Test cases (static user) • IGS station • Field receiver in 3 observation environments • Regional PPP service using GLONASS (GPS+GLONASS) • IGS data or SDCM if available • Similar test cases as for EGNOS/GPS EEGS IRKP2 Meeting

  19. WP5: Dissemination Activities Activities done in the period: • WP 5.1: Dissemination Plan • WP 5.1.1: MAO provides template and guidelines: done • WP 5.1.2/3/4/5/6: SRC/ROSA/RSS/GMV/AENA contribute to dissemination plan: no contribution up to IRKP2 (as far as we know). All partners to provide contributions. Action to be taken in the MoM. • WP 5.1.7: MAO contributes and delivers officially the plan at MTR • WP 5.2: Results dissemination: to be started after MTR EEGS IRKP2 Meeting

  20. Thank you

More Related