1 / 36

Maury Galbraith Northwest Power and Conservation Council Portland, OR August 21, 2008

Sixth Northwest Conservation & Electric Power Plan Actual vs. Modeled Operation of Combined-Cycle Combustion Turbines in the Pacific Northwest. Maury Galbraith Northwest Power and Conservation Council Portland, OR August 21, 2008.

Download Presentation

Maury Galbraith Northwest Power and Conservation Council Portland, OR August 21, 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sixth Northwest Conservation & Electric Power PlanActual vs. Modeled Operation of Combined-Cycle Combustion Turbines in the Pacific Northwest Maury Galbraith Northwest Power and Conservation Council Portland, OR August 21, 2008

  2. Excessive Shutdown Disorder: condition where modeled operation of CCCTs exhibit more stops (and starts) than actual operation. July 17, 2008

  3. Q: How do you know if you have excessive shutdown disorder? A: Get EPA’s Continuous Emissions Monitoring System (CEMS) data. July 17, 2008

  4. Pacific Northwest CCCT Dataset • EPA CEMS Data: 2006 – Q1 2008 • Hourly Operating Data: 19,704 hours • Generating Unit Data: • Aggregate to plant level • Gross Generation (in MW) • For gas turbines only (not for HRSGs) • Fuel Input (in MMBtu) • Fuel Factor (i.e., Hourly Fuel Input / Max(Fuel Input)) as proxy for CCCT capacity factor July 17, 2008

  5. Northwest CCCTs in CEMS Database July 17, 2008

  6. Coyote Springs 1: Actual Operation in 2007 July 17, 2008

  7. Coyote Springs 1: Modeled Operation in 2007 July 17, 2008

  8. Coyote Springs 1: Actual Week Summer July 17, 2008

  9. Coyote Springs 1: Modeled Week Summer July 17, 2008

  10. Hermiston Power: Actual Operation in 2007 July 17, 2008

  11. Hermiston Power: Modeled Operation in 2007 July 17, 2008

  12. Klamath Cogen: Actual Operation in 2007 July 17, 2008

  13. Klamath Cogen: Modeled Operation in 2007 July 17, 2008

  14. More modeled starts per year… July 17, 2008

  15. Much shorter modeled runtimes… July 17, 2008

  16. Q: Why is excessive shutdown an important problem? A: Because it impacts: • wholesale power market price forecasts; and • power system carbon dioxide forecasts July 17, 2008

  17. AURORA CCCT Commitment and Dispatch Parameters July 17, 2008

  18. MIN UP Estimation July 17, 2008

  19. Coyote Springs 1: Actual Up Time HistogramN = 30 July 17, 2008

  20. Chehalis: Actual Up Time HistogramN = 78 July 17, 2008

  21. PNW CCCTs: Actual Up Time HistogramN = 1,114 July 17, 2008

  22. PNW CCCTs: Actual Up Time HistogramN = 759 Min Up = 17 hours July 17, 2008

  23. MIN Down Estimation July 17, 2008

  24. PNW CCCTs: Actual Down Time HistogramN = 1,113 July 17, 2008

  25. PNW CCCTs: Actual Down Time HistogramN = 749 Min Down = 3 hours July 17, 2008

  26. MIN Capacity Estimation July 17, 2008

  27. Coyote Springs 1: Cumulative Frequency of Operating Level (N = 14,180 hours) July 17, 2008

  28. Big Hanaford: Cumulative Frequency of Operating Level (N = 4,964) July 17, 2008

  29. Chehalis: Cumulative Frequency of Operating Level (N = 9,601 hours) July 17, 2008

  30. PNW CCCTs: Cumulative Frequency of Operating Level Curves July 17, 2008

  31. Ramp Rate Estimation July 17, 2008

  32. Coyote Springs 1: Ramp Rate Illustration July 17, 2008

  33. Minimum Number of Hours to Heat Input Factor > = .85 July 17, 2008

  34. Minimum Number of Hours to Heat Input Factor > = .90 July 17, 2008

  35. Minimum Number of Hours to Heat Input Factor > = .95 July 17, 2008

  36. Next Steps: • Firm-up existing unit and new technology operating parameters • Estimate Start-up and Shut-down costs • Use AURORA’s new “shutdown penalty” to adjust modeled CCCT operation July 17, 2008

More Related