1 / 13

California’s Expedited Power Plant Permitting Processes Roger Johnson Siting Office Manager

California’s Expedited Power Plant Permitting Processes Roger Johnson Siting Office Manager. California Energy Commission March 15, 2001. Topics. Governor declares energy emergency Governor’s Executive Orders Expedited Permitting Processes Emergency Permit Review Status.

herschel
Download Presentation

California’s Expedited Power Plant Permitting Processes Roger Johnson Siting Office Manager

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. California’s Expedited Power PlantPermitting ProcessesRoger JohnsonSiting Office Manager California Energy Commission March 15, 2001

  2. Topics • Governor declares energy emergency • Governor’s Executive Orders • Expedited Permitting Processes • Emergency Permit Review Status

  3. Governor’s Executive Orders • 6 Executive Orders Issued February 8 • 1 Executive Order Issued March 7 • Focused on power plants • Planning • Siting • Permitting • Construction • Operation

  4. Governor’s EO’sLicensing • Maintain 12-month AFC • Maintain 6-month AFC • Reestablish 4-month AFC • Establish emergency permit process • Establish 45-day amendment • Establish 7-day amendment

  5. 6-month AFC • Purpose - Expedite “clean” projects • Projects • No public health or safety concerns • Mitigated environmental impact • No significant adverse energy system impact • Comply with legal requirements • Have a contract and skilled labor • Address disproportionate impacts • Control site • Priority for “superior” projects

  6. 4-month AFC • Purpose - Peaking projects • Data adequate by Dec. 31, 2001 • On line by Aug 2002 • Projects • No public health or safety concerns • Mitigated environmental impact • No significant adverse energy system impact • Comply with legal requirements • Have a contract and skilled labor • Address disproportionate impacts • Control site

  7. Emergency Permit • Who Qualifies? • Peaker power plant • On line by September 30, 2001 • ISO Summer Reliability Contract • 50 MW or larger • No fatal flaws

  8. Emergency Permit • Length of CEC license • Life of project if: • contract with CDWR or CAISO • meets continuation criteria at end of contract: • meets BACT and has permanent air emission offsets • compliance with all Energy Commission conditions • site control, and • project is a permanent facility. • 3 years with option to recertify w/o contract

  9. Emergency Permit • Purpose - Peaking projects • Fatal Flaw Analysis • No public health or safety concerns • Mitigated environmental impact • No significant adverse energy system impact • Comply with legal requirements • Have a contract and skilled labor • Address disproportionate impacts • Control site • No or minimal linear facilities • Exempt from CEQA requirements

  10. Emergency PermitSchedule

  11. Emergency PermittingStatus • Executive Orders D22-D27 February 8 • Process defined February 27 • Executive Order D28 March 7 • First two applications filed March 8

  12. Emergency Power Plant Permits Under CEC Review Note: Intergen Wildflower projects were previously known as Tejas 1, 2, 3, 4, and 5

  13. More Information • Energy Commission • Roger Johnson (916) 654-5100 • Toll free Hot Line in CA (888) 871-9673 • www.energy.ca.gov/sitingcases/peakers • Air Resources Board • Michael Tollstrup (916) 322-6026 • www.arb.ca.gov/energy/energy.htm • Department of Water Resources • Viju Patel (916) 952-0926

More Related