1 / 14

UW-Provision Company

UW-Provision Company. Outline. Introduction Project Team Client Client Background Problem Criteria Best Practices Alternatives Considered. Outline (cont.). Data Used Recommendations Expected Benefits Plans for Implementation Lessons Learned. Introduction. Project Team

hiroko
Download Presentation

UW-Provision Company

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UW-Provision Company

  2. Outline • Introduction • Project Team • Client • Client Background • Problem Criteria • Best Practices • Alternatives Considered

  3. Outline (cont.) • Data Used • Recommendations • Expected Benefits • Plans for Implementation • Lessons Learned

  4. Introduction Project Team • Josh Miller: Team Leader • Kate Porcaro: Web Master • Raeleah Wentland: Client Liaison Client – UW-Provisions • Steve Kalscheur: Employee Contact

  5. Client Background UWP—”The Meat People” • Meat warehouse and distribution center • Located in Middleton, WI. • Approximately 5000 products - pork - poultry - beef - fish

  6. Problem Criteria • UWP Freezer System - Freezer system is unorganized - Difficulties in finding product - Too many products; Too little space • Our Goal - Reduce multiple handling of products • Increase the speed with which orders are picked • Improve safety

  7. Best Practices • Menards • United Parcel Service (UPS) • United States Post Office • Wis-Pak Foods

  8. Alternatives Considered • Do nothing • Implement a plant automation system • Add an additional freezer • Redesign freezer layout and organization system

  9. Data Used • Freezer dimensions • Storage rack dimensions • Inventory lists including product weights and order frequencies

  10. Recommendations • Three freezers with organization by product type • Products should have one functional location • Color-coded racks by product type • Replace racks and increase aisle widths in freezer 5

  11. Expected Benefits • Reduce cost • Reduce training time • Increase safety • Possible to implement in other areas of company

  12. Plans for Implementation • Clean all freezers and reduce inventory • Color-code all designated areas • Allocate temporary storage space • Complete in one day

  13. Lessons Learned • Be specific with project scope • Be in constant contact with client • Seek their needs • Listen closely to their desires • Satisfy all customers • Simple solution is best

  14. Questions?

More Related