SIS 2006 Update. June 28, 2006. Big Picture. Design Phase Preparatory Projects Phase – April 24 – August 4 Configuration Documentation & Testing Site preps Implementation – ?August 18? – ?????. Implementation. Weeks 1 – 3 – Test & Migrate Bismarck-Fargo ATMs to RPR
E N D
SIS 2006 Update June 28, 2006
Big Picture • Design Phase • Preparatory Projects Phase – April 24 – August 4 • Configuration Documentation & Testing • Site preps • Implementation – ?August 18?– ?????
Implementation • Weeks 1 – 3 – Test & Migrate Bismarck-Fargo ATMs to RPR • Week 4 & 5 – Burn-in time for RPR, Prep for PSD migration • Week 6 & 7 – Migrate PSD • Week 8 & 9 – Migrate I2 and prep for K12 • Week 10 & 11 – Migrate K12 • Week 12 - 15 – Migrate K12 Video • Week 16 - 18 – Prep & Migrate State • Weeks 19 – 21 – Prep & Migrate HE
Current Risks/Issues • Continued delay in DCN turnover • Risk mitigated as best as possible • DCN power not installed as scheduled New Risk • Could be quality issue with RPR
Good News • Most of the equipment has arrived • Configuration & testing is well under way. • New video configuration is looking good
More Information • Next IVN Session = July 26 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Conceptual diagrams • Dirk Huggett • dhuggett@nd.gov • 701-223-2248