SIS 2006 Update Executive Steering Committee. June 30, 2006. Status. Overall Status – Yellow Scope – Green Schedule – Red Cost – Green Risk - Green. Key Accomplishments . Completed Phase 2 Planned out and scheduled Phase 3 Completed the design elements Ordered equipment
E N D
SIS 2006 UpdateExecutive Steering Committee June 30, 2006
Status • Overall Status – Yellow • Scope – Green • Schedule – Red • Cost – Green • Risk - Green
Key Accomplishments • Completed Phase 2 • Planned out and scheduled Phase 3 • Completed the design elements • Ordered equipment • On track for pre-migration tasks
Current Risks/Issues • Continued delay in DCN turnover • Risk mitigated as best as possible • DCN power not installed as scheduled New Risk • Could be quality issue with RPR
Implementation • Weeks 1 – 3 – Test & Migrate Bismarck-Fargo ATMs to RPR • Week 4 & 5 – Burn-in time for RPR, Prep for PSD migration • Week 6 & 7 – Migrate PSD • Week 8 & 9 – Migrate I2 and prep for K12 • Week 10 & 11 – Migrate K12 • Week 12 - 15 – Migrate K12 Video • Week 16 - 18 – Prep & Migrate State • Weeks 19 – 21 – Prep & Migrate HE
More Information • Next IVN Session = July 26 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Conceptual diagrams • Dirk Huggett • dhuggett@nd.gov • 701-223-2248