SIS 2006 Update. March 22, 2006. Big Picture. Design Phase – April 13 Conceptual Design, Final Design Draft Design Phase – May 30 Configuration Documentation & Testing Preparatory Projects Phase – April 17 – May 30
E N D
SIS 2006 Update March 22, 2006
Big Picture • Design Phase – April 13 • Conceptual Design, Final Design Draft • Design Phase – May 30 • Configuration Documentation & Testing • Preparatory Projects Phase – April 17 – May 30 • Reconfigure K12/HAN/Library, Replace current HECN routers, Video testing, local projets • Implementation – June 12 – August 18 • Details to be determined
Design • Conceptual Design is due March 24 • Physical Designs due April 13 • Start equipment orders following week • Includes order lag time and setup time • Document Configuration • Perform Testing
Preparatory Projects Phase • Things we can do before the actual implementation • Planning the details now – Draft Due April 13
Implementation Phase • Can’t be determined until many of the design tasks completed • Planning for it will occur through the month of May • Intend to have at least K12 & HE completed by August deadline
Current Risks • Weather in the Red River Valley • Several fiber runs to be completed • Compressed timeline may impact “burn-in” time • New Technology