Prepared by: James Klang, P.E., Senior Project Engineer And Gwen Ryskamp, Intern. Overview of the Clean Water Act. Jim Klang, PE 536 E. Michigan Ave / Suite 300 Kalamazoo, MI 49007. History of the Clean Water Act. 1972 -- US congress passed the Clean Water Act

hop-gibson
Download Presentation

Overview of the Clean Water Act

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Prepared by: James Klang, P.E., Senior Project Engineer And Gwen Ryskamp, Intern Overview of the Clean Water Act Jim Klang, PE 536 E. Michigan Ave / Suite 300 Kalamazoo, MI 49007

  2. History of the Clean Water Act • 1972 -- US congress passed the Clean Water Act • Response to national concern: • 1968 Cuyahoga River, Ohio burns • Lake Erie was a “Dead Zone” • Eutrophic • 12 WWTPs discharged over 39,600 lbs/day of TP • Blue Green Algae • Low dissolved oxygen; fish kills • Toxic; wildlife killed • First Earth Day: April 22, 1970 Photo Credit: Time Magazine

  3. Clean Water Act: Regulated Clean Water Act (authors initial perspective): Address wastewater loading  solves most of the nation’s water quality problems • All waters protected (Beneficial Uses, standards) • Wastewater treatment facility permits • Secondary effluent limits (25 mg/l CBOD, 30 mg/l TSS) • Waste load studies set advanced treatment limits • Municipalities received financial assistance • Total Maximum Daily Load (TMDL) requirements

  4. Clean Water Act: Unregulated • Certain nonpoint source pollutant reduction categories are voluntary • Provides for watershed plans • Provides nonpoint source (NPS) incentives • Section 319 Photo courtesy of USDA NRCS.  • In the 1980s, Courts required TMDL be applied to NPS, in a voluntary context.

  5. Urban Voluntary Programs • Stormwater, small rural cities • Additional Funding: • Farm Bill • Section 319 • “Voluntary” sources can generate credits to sell, or buy credits Photo courtesy of USDA NRCS. 

  6. Urban Regulatory Programs • National Pollutant Discharge Elimination System permits (NPDES): • Municipal Wastewater Treatment Facilities • Large city Phase I stormwater MS4s • Medium city Phase II stormwater MS4s • Construction stormwater • These permits address several Clean Water Act provisions (next slide) Photo courtesy of US EPA. 

  7. Urban Regulatory Programs(Continued) • Municipal wastewater permit effluent limits • Secondary treatment • Advanced treatment • Stormwater management plan programs • Effluent limits stated in Best Management Practices • Maximum Extent Practicable Photo courtesy of USDA NRCS.  • TMDL studies set load allocations limits for both stormwater and wastewater • Stormwater permits bound by Maximum Extent Practicable can not generate credits to sell, but can buy

  8. Urban Regulatory Programs(Concluded) Permits provide for: • Waste load allocations (advanced treatment requirements) without TMDLs • Antidegradation (Federal) & Nondegradation (State) • Antibacksliding • Industrial Pretreatment Consideration of the compliance status of these CWA provisions helps determine the minimum baselines before water quality trading credits can be bought or sold

  9. Agricultural Voluntary Programs • Row cropping • Very small livestock feeding operations • Pasturing • Livestock exclusion from streams TMDL activities set load allocations;compliance met via education and incentive programs Photo courtesy of USDA NRCS. 

  10. Agricultural Regulatory Programs • Larger sized animal feeding operations • 1000 animals NPDES permit • Zero discharge from production lot • Manure land application set backs, nutrient management and incorporation requirements • Medium sized animal feeding • 50 to 999 (10 on shore land)  registration with RGU required • RGU decides if further requirements apply or local government permits required Photo courtesy of USDA NRCS. 

  11. Individual Septic Treatment Systems • Federal Court decided: • These are regulated sources • They must appear in the Waste Load allocation portion of the TMDLs • Granted zero allocations Therefore not eligible for water quality trading in Minnesota Double deck privy. Pennsylvania. Photo date between 1935 and 1942 Source: Library of Congress, Prints & Photographs Division, FSA-OWI Collection, Reproduction number LC-USF344-007504-ZB DLC

  12. Regulator Support of Water Quality Credit Trading • EPA approved a Water Quality Trading Policy in 2003, since has provided more guidance • Farm Bill supports and promotes Ecosystem Service markets (includes water quality trading) • Water Quality Trading is the only program that can reallocate a TMDL without reopening it • Minnesota Pollution Control Agency is currently promulgating rules on Water Quality Trading

  13. In Conclusion Water Quality Trading: • Works with the Clean Water Act as a foundation • Recognizes and uses the inequities in CWA regulatory requirements to your advantage • Adjusts allocations Without reopening a TMDL: • Assesses the minimum requirements of each sector • Not usable if trading causes or contributes to a water quality problem • Addresses only persistent parameters, not whole treatment • Targets high cost differences in pollutant load reductions • Creates cost savings for both parties; win-win • Uses legally binding agreements for non-permitted participants • Addresses multi-source contribution problems best