170 likes | 298 Views
Utility Planning For North Campus Upgrades. Area in and around Cook Physical Science Building. A Conceptual Plan……. Sal Chiarelli, Director of Physical Plant November 15, 2007. Why Is This Important.
E N D
Utility Planning For North Campus Upgrades Area in and around Cook Physical Science Building A Conceptual Plan……. Sal Chiarelli, Director of Physical Plant November 15, 2007
Why Is This Important This Is Conceptual But Presenting A Long Term View Of The Utility Upgrade Possibilities When We Design And Build The Cook Science Expansion • Do not want to miss out on the opportunity to solve many issues while planning for Cook • We need to do many of the upgrades any way • Prepare for future projects in and around Cook • Provide robust utility system for reliability, availability and maintainability • Most likely going to Air Condition Williams in the future if renovated • Has the potential to save
Some Deficiencies In And Around Area • Undersize and old piping sections • Have to relocate piping in order to fit building on East side • Chilled water system capacity will be depleted when Plant Science, Marsh, and Billings, Votey and Kalkin are hooked up. • Need cooling capacity for Williams, Cook 1, Cook 2 • Better to send out lower pressure on campus
Some Opportunities • Generate electrical power maybe 2MW • Provide chilled water to Cook and Cook 2 • Provide chilled water to Billings • Provide chilled water to Williams Hall • Distribute steam at a lower pressure • Use back pressure turbine to reduce steam pressure • Use daytime chilling capacity to store chilled water or ice at night off peak hours • Use heating and chilled systems as part of the engineering curriculum • Use excavation to maximize utility and energy systems in and around Area • This is the “green thing” to do for the future • Build in redundancy for reliable utility distribution
Some Benefits • Maximizing the use of steam pressure • Historic building air conditioning • Real time, real life engineering and economics study- relate to theory with adjacent to/ or in new science building…….. • We will need more chilled water than our plant can deliver when Cook buildings are initiated • Back feed to Given provides steam redundancy on distribution including CBW and Converse….. • If sized correctly steam can power up HSRF chiller to provide summer load for turbine generator set. • Do we need more air conditioned “Bed Space”….? • We have infrastructure for this type of system
Engineering School and Other Teaching Thoughts • Thermo Dynamics • Vibration studies • Fluid Mechanics • Material selections and metallurgy • Theory of machines and rotating equipment • Heat Transfer • Many other courses and programs could utilize systems. • Real time data used for study • Real equipment available for students and faculty to use in studies. • Use the tens of millions of dollars investment for the study of engineering • Economic analysis of fuel use and energy consumption • Other cool stuff..
If We Don’t Do This • We will have to replace old deteriorated steam lines anyway on East side of Cook and north side of Cook by Votey (see Pictures) • We will eventually air condition Williams Waterman, and tie our central system into Votey, Kalkin and Billings, • We will spend more on operating costs • We will not maximize the use of existing systems.
Some Steps To Take • Replace/Relocate line on east side of Cook • Add chilled water lines to Cook • Add chilled water lines to Kalkin/Votey • Connect LP Steam to CBW to feed Converse and possibly Given • Investigate night time storage of chilled water or ice • Possibly relocate chillers to assist in chilled water plant operations • Connect Billings, Williams and loop back to Old Mill with LP steam • Add Topping Turbine to Cook or Central Plant with exhaust steam powering LP loop • Install electrical distribution system to power Cook, Cook 2, Old Mill, Library, Davis, Votey, RTT, Kalkin • “Engineer the entire area for the future • Install Electrical Distribution network..
Slide Showing Buildings Need To Scroll Down For Full View
Conclusion Slide Showing Existing Lines
Conclusion Slide Showing Possible Cook Addition
Conclusion Slide Showing Proposed New Chilled Water and Steam
Conclusion Slide Showing Proposed New Chilled Water and Steam
Conclusion Slide Showing Proposed New Chilled Water and Steam And Need For Electrical Distribution
Conclusion • This concept needs to be studied for cost, economic feasibility, life cycle, viability. • I think it is more palatable than a full blown 5Megawatt Cogeneration system • Up to 2MW may be OK with BED • We need to do some of this anyway let’s do it in a systematic, long term way. • It would be awesome for the Engineering School to have some of these systems as part of their learning curriculum