1 / 17

Xcel Energy and Environmental Parties Least-Cost Resource Plan Settlement Agreement

Xcel Energy and Environmental Parties Least-Cost Resource Plan Settlement Agreement. Discussion. Background Negotiations Implementation Lessons Learned. Xcel Energy in Colorado. 1.34 million electric customers 1.25 million natural gas customers Provides energy to 75% of state’s residents.

isanne
Download Presentation

Xcel Energy and Environmental Parties Least-Cost Resource Plan Settlement Agreement

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Xcel Energy and Environmental PartiesLeast-Cost Resource Plan Settlement Agreement

  2. Discussion • Background • Negotiations • Implementation • Lessons Learned

  3. Xcel Energy in Colorado • 1.34 million electric customers • 1.25 million natural gas customers • Provides energy to 75% of state’s residents

  4. The Least-Cost Plan Filing Filed with the CPUC April 30, 2004 • Forecast of electric needs from 2004-2013 and plan to meet them • Included: • Proposed all-source bidding process • A request to build a 750 MW coal-fired unit at Comanche Station near Pueblo

  5. The Forecast

  6. Process • Resource forecast and plan filed 4/30/04 • Rounds of testimony filed • In fall 2004, negotiations began with two main groups: • Environmental and community parties • Other intervenors (OCC, PUC staff, others) • Hearings held at CPUC Nov. 2004

  7. Why Negotiate? • Environmental groups’ view: • Reduce environmental impact of new coal unit • Greater environmental benefits faster • Achieve specific environmental benefits for Pueblo community • Expand renewable energy and energy conservation • Develop ongoing dialogue • Accountability

  8. Why Negotiate? • Xcel Energy’s view: • Cooperation and consensus from intervenors concerning critical energy resource • Reduce litigation risk concerning Comanche project • Opportunity to install additional emission controls on existing facility • Enhance community relations • Establish dialogue and pursue opportunities for mutual collaboration

  9. Negotiation Process • Negotiators • Major environmental and community parties; Xcel Energy • Long, difficult discussions with compromise from both sides • Key challenges: • Environmental negotiators – negotiating on behalf of many parties with different interests • Utility negotiators – balancing interests of many different parties; outside involvement in how we run our business; long-term implications and policy impacts • A common challenge: Internal buy-in

  10. Settlement Agreement • Reached Dec. 2004; PUC approved 1/05 • Concerned Environmental and Community Parties (CECP): • Sierra Club • Western Resource Advocates • Environmental Defense • Better Pueblo • Diocese of Pueblo • Southwestern Energy Efficiency Project • Colorado Renewable Energy Society • Environment Colorado • Smart Growth Advocates

  11. Key Provisions • Comanche • Additional emission controls and tighter emission limits for Comanche Station • Mercury testing and cost-effective controls for all units; plant-wide mercury emission limit • Energy planning • Accept wind bids up to 15% penetration if in least-cost portfolio • Wind ancillary cost study • Greatly increased energy conservation programs and study • New resources evaluated with CO2 proxy cost and renewable energy credit value • Innovative technologies • Community initiatives • Pueblo environmental donations and community involvement

  12. Key Provisions • Agreement by environmental signatories not to oppose Comanche Station permitting and approval processes Agreement on web site www.xcelenergy.com, under Energy and Rates, Colorado least-cost resource plan

  13. Comanche Station Emission Controls Existing and New

  14. Implementation • Quarterly meetings • Ongoing involvement • Wind study • Demand side management working group • Pueblo initiatives • Legislative agenda • Different groups have different interests

  15. Ongoing Issues and Challenges • Lawsuit challenging air permits for Comanche project • Not filed by CECP • Impact on future negotiated settlements • Communication

  16. Lessons Learned • Collaboration is possible • Effort and personal commitment to get it done

More Related