RIGO Update Xcel Energy

RIGO Update Xcel Energy. Jason Standing Jeffrey Norman October 3, 2007. Updates Since Last Meeting. Options 1,2,3, and 4 (western options) have been dismissed as possible options. Focus instead on the southeastern portion of Minnesota. Created a few combination options.

lee
Download Presentation

RIGO Update Xcel Energy

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RIGO UpdateXcel Energy Jason Standing Jeffrey Norman October 3, 2007

  2. Updates Since Last Meeting • Options 1,2,3, and 4 (western options) have been dismissed as possible options. • Focus instead on the southeastern portion of Minnesota. • Created a few combination options.

  3. Option 5: Owatonna-Austin Corner 161 kV • 53 MW of outlet • Option 5b • Second Pleasant Valley 345/161 kV line • 308 MW of outlet

  4. Option 8: Blue Earth-Loon Lake 161 kV • 220 MW of outlet

  5. Option 9: Pleasant Valley-Blue Earth 161 kV • 43 MW of outlet • Option 9b • Second Pleasant Valley 345/161 kV line • 330 MW of outlet

  6. Option 11: Loon Lake-Jackson 161 kV • 130 MW of outlet • Option 11a • Reconductor of the Lakefield-Triboji 161 kV line • 255 MW of outlet

  7. Option 5b9: Owatonna-Austin Corner 161 kV Pleasant Valley-Blue Earth 161 kV Pleasant Valley 345/161 kV tx 268 MW of outlet Option 5b9a Second Maple Leaf-Byron circuit 412 MW of outlet Option 5b9ab Option 5b9a with tripping of new generation for loss of Pleasant Valley 345/161 tx 617 MW of outlet Option 5b9

  8. Option 89: Pleasant Valley-Blue Earth-Loon Lake 161 kV • 47 MW of outlet • Option 89a • Second Pleasant Valley 345/161 kV tx • 365 MW of outlet • Option 89ab • Second Maple Leaf-Byron circuit • 572 MW of outlet

  9. Where to go from here? • Run a few more sensitivity cases. • Determine which option to go forward with. • Write up a draft report and send it out for review. • Write the final report.