1 / 24

14 th Crystal Ball Meeting Edinburgh September 13.-15. 2009 Andreas Thomas

Overview installation of Polarized Target . 0.- Hydrogen Target Length 1 .- Polarized target tests 2.- Rail System for ‘Frozen Spin’ mode 3.- CB Frame / Electronics 4.- Schedule. 14 th Crystal Ball Meeting Edinburgh September 13.-15. 2009 Andreas Thomas.

istas
Download Presentation

14 th Crystal Ball Meeting Edinburgh September 13.-15. 2009 Andreas Thomas

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OverviewinstallationofPolarized Target 0.- Hydrogen Target Length 1.- Polarized target tests 2.- Rail System for ‘Frozen Spin’ mode 3.- CB Frame / Electronics 4.- Schedule 14thCrystal Ball Meeting Edinburgh September 13.-15. 2009 Andreas Thomas

  2. Note: Hydrogen Target Length New Xraypictureof 30mm cellat 9.9.09 [R.Kondratiev, O.Kostikov, A.Thomas] • Results: • 3 cm cell 30.2 +- 0.3 mm h - Bump • 5 cm cell 47.2 +- 0.5 mm standard • 10 cm cell 100.0 +- 1.0 mm High luminosity

  3. Components of the polarized target for the Crystal Ball detector He3/He4 Roots 4000m3/h Vacuum system Targetmaterial H-Butanol D-Butanol Mikrowaves 70GHz Dynamic Nuclear Polarization Superconducting Polarization magnet 5Tesla NMR-Apparatus 106MHz Polarisation meas. Horizontal He3/He4 Dilutionrefrigerator (20mKelvin) with internal Holding coil

  4. ·  Current leads (46A): Copper T=300K  70 K HTc Supracond. T= 70K  4 K NbTi 200mm T= 4K  1.5K Internal Holding coil 1.3Kelvin ??? Tesla at 46A L=136mm, d=48mm, 4 layers Support Copper-tube d=0.3mm

  5. Fulltestwithnewinsertandbutanoltarget in June – July 2009

  6. Polarizing magnet He4(liq)

  7. Start

  8. Stop

  9. Calibrationofthe Holding coilfield B0=2.5Tesla F= 106MHz Observeshiftof NMR-Signal depending on holdingcoilcurrent

  10. B0=2.5Tesla F= 106MHz 46A ~ 0.895Tesla

  11. Internal transverse Holding coil Coiltestedat 4.2K Henry Ortega StartedPhD in Mainz Different layersare usedto optimizethe homogeniety.

  12. Simulation • “Racetrack” coil: magnetic field highly non-uniform and not appropriate for a cylinder. • “Saddle” coil: winding must fit to the so-called overlapping ellipse or “cosine” shape of current distribution (Wilson 2002 & Ašner 1999). Ideal case for dipole magnet:

  13. 4-layer dipole: N1=N2=138 N3=N4=78 150mm

  14. High Field Solenoid or Transverse Field

  15. The degreeofpolarizationPTofthetargetprotons (runin May ´98) : Measurement ofthedegree ofprotonpolarization with online NMR during GDH datataking New NMR  [N.Frömmgen]

  16. Crystal Ball Polarizing magnet Polarizing magnet Cryostat Microwaves Microwaves + NMR Rail system needed Polarization method • External magnet 2.5 T • Polarize with microwaves • Internal holding coil 0.7 T • Remove external magnet • Move CB detector in. • Data taking. • Repolarization

  17. Rail system to Move the CBall, TAPS and Magnet ACAD rails J.Rosche Chassis J.Ahrens Electronics A.Starostin P.Pedroni Move magnet transverse A.Thomas

  18. Railsarebeeingaligned andfixed: R.Kondratiev O.Kostikov

  19. Heavy loadcars will bemounted byJ.Ahrensnextweek

  20. Electronics hastobemounted partially on CB frame: A.Starostin A.Lapik M. Korolija

  21. Schedule 1.- Polarized Target - tests in dilution mode reproduced successfully - transverse coil tested at 4K - DNP measured - ColleaguesfromDubna in Mainz Nov.-Dec. 2.- Rail system for CBall - Cables dismounted, Railsbeeingalignednow - First moveof CB nextweek - DAPHNE in storage hall, TOF detectors? - Installation ofpartofelectronics in CB-Frame? 3.- Installation of PT in CBall - Start in October - Test beam in Decemberforintensitydependentrelaxation time etc. - Transverse or Longitudinal coil.

More Related