Support Graphics for Traffic and Circulation Princeton Junction Redevelopment Area Township of West Windsor September 8, 2008 Urbitran | DMJM Harris. ENG-WONG, TAUB TRAFFIC ASSESSMENT REPORT.
E N D
Support Graphics for Traffic and Circulation Princeton Junction Redevelopment Area Township of West Windsor September 8, 2008 Urbitran | DMJM Harris
ENG-WONG, TAUBTRAFFIC ASSESSMENT REPORT • It is important to note that the results of this “pre-conceptual” analysis are based on …. Preliminary assumptions and would likely change based on changes in background regional traffic volumes associated with revisions to the NJDOT Penns Neck model (i.e., with the Vaughn Drive Connector included as a stand-alone improvement without any of the US-1 upgradws previously identified in the Penns Neck EIS). • Principal objectives • Confirm findings of my initial “sketch” analysis (3/31/08) • More specific traffic data to guide sizing and layout of streets and intersections
2030 No-BuildLevels of Service LOS A-D LOS E LOS F
2030 No-Build Assessment • This analysis indicates that at each of the three signalized intersections in the Study Area, traffic volumes will exceed capacity even with no further development action within the redevelopment area and if no further mitigation is applied. In considering alternatives for the Route 571 improvement, the Township clearly articulated its objective to limit roadway widening, even if congestion were to result. The findings of this analysis are consistent with that position. • 3/31/08 memo re. Hillier • 9/08/08 memo re. InterCap
2030 BuildLevels of Service Improvements Assumed LOS A-D LOS E LOS F
On-SiteTraffic Volumes 680 1170 950 2415 1010 1480 Highest hourly 2-directional volume 650
INTERCAP REDEVELOPMENT PLAN REVIEW • Traffic Access (1-7) • West-Side Circulation (8-13) • East-Side Circulation (14) • Main Street (Route 571 Area) (15-17) • Parking (18-21) • Pedestrians and Bicycles (22-24) • Finance (25-29)
Traffic Access:(3) Further improvements needed at Alexander / Vaughn
Traffic Access:(4) 4 lanes needed on Vaughn Drive: Remove Parking
Traffic Access:(5) Eliminate grade separations, 2 at-grade intersections
Traffic Access:(6) Extend Vaughn Drive or Road B to Sarnoff Connector (Vaughn Drive preferable)
Traffic Access:(7) NJDOT evaluating implications of changing Penns Neck EIS Record of Decision plan
West Side Circulation:(8) Core Area: More detail needed, accomodation for drop-offs / pickups, BRT, etc.
West Side Circulation:(9) Core Area: A plan can be worked out
West Side Circulation:(10) Core Area: Additional pedestrian tunnel
West Side Circulation:(11) “X” arrangement for primary streets Primary intersection at crossing
West Side Circulation:(12) Seek appropriate volume and mix on Road B in town center
West Side Circulation:(13) Reexamine use of Vaughn Drive and BRT line
Main Street (Route 571) Area:(15) Consistency with adopted concept
Parking:(18) Parking space supply Site Uses (5,650 spaces) New Commuters (2,500 spaces) Existing Commuters (3,500 spaces)
Parking:(19) BRT impact on parking demand1000-1200 space reduction in demand(20) Accounting for shared parking in new non-commuter space calculations(21) Garage layouts, sizes, access, general arrangement
Pedestrians and Bicycles:(23) Pedestrian plan and links to Township System
Pedestrians and Bicycles:(24) Pedestrian bridge at Route 571 / Amtrack
Pedestrians and Bicycles:(25) Add pedestrian links, fill gaps
Finance:(25) Infrastructure financing not analyzed by me(26) Basis of initial cost estimate not presented(27) Cost reductions being investigated - Eliminate grade separations - Effect on Penns Neck EIS being evaluated - Added cost items probable(28) Vaughn Drive on Township Roadway Assessment program(29) State funding implies need for flexibility in layout, phasing, financing