Analog System Review and Status Wes Grammer NRAO EOVSA Prototype Review
Outline • Top-level subsystem description • Module-level design and construction status • 2-meter Front End assembly • Front End auxiliary electronics cabinet • Downconverter module • LO Distribution modules • Timing Generation and Distribution module • Correlator Clock Generation module • Rack-level design & cabling • Budget and current schedule EOVSA Prototype Review
Analog Subsystem Diagram EOVSA Prototype Review
2-Meter Front End Assembly EOVSA Prototype Review
2-Meter Front End Block Diagram EOVSA Prototype Review
Half-side Interior View,2-meter Front End Assembly EOVSA Prototype Review
20 GHz Laser Transmitter EOVSA Prototype Review
Optical Mux / Demux EOVSA Prototype Review
Front End Module Design and Construction Current status • Most components on hand, except low-loss coax cables, BPF, bulkhead fiber adapter. • Module mechanical design 50% done; will contract Segars Engineering to complete. • Apex mounting plate design is TBD (Segars ) • Module wiring diagram is TBD • Ethernet cable is under construction (Kjell N.) • Front End interface board circuit design 90% done; PCB layout, fab and assembly TBD. Parts ordering TBD. • Software interface document, embedded firmware and control GUI are TBD. EOVSA Prototype Review
Front End Auxiliary Cabinet EOVSA Prototype Review
Auxiliary Cabinet Wiring Diagram EOVSA Prototype Review
Auxiliary Cabinet Design and Construction Current status • Nearly all components on hand; two Lambda supplies on backorder, opt. RX units in transit. • Wiring of first cabinet is well underway • All 4 power and signal cables completely specified, parts on hand at OVRO (Kjell to build) • 1PPS fiber patch cords on order; will arrive ~9/28 • Outdoor analog fiber drop cables on order; will arrive ~11/1. • Ethernet cable under construction (Kjell N.) • Multifiber cable termination inside cabinet TBD EOVSA Prototype Review
Downconverter Module EOVSA Prototype Review
Downconverter Block Diagram (1 of 2) EOVSA Prototype Review
Downconverter Block Diagram (2 of 2) EOVSA Prototype Review
Downconverter Module Interior Layout EOVSA Prototype Review
Downconverter Front/Rear Panels EOVSA Prototype Review
Downconverter Module Interface PCB EOVSA Prototype Review
Downconverter Module Design and Construction - Current status • All components in, except one 2.92mm cable • Module mechanical design complete, metal work on order. Assembly drawings TBD. • Need to generate module wiring diagram; mechanical assembly of 1st module will begin ~ Oct. 8. • Downconverter interface board in assembly stage, firmware development and GUI TBD. • Rack DC power cables under construction EOVSA Prototype Review
LO Distribution Module EOVSA Prototype Review
LO Distribution Subsystem: LO1 EOVSA Prototype Review
LO Distribution Subsystem: LO2, DC input EOVSA Prototype Review
LO1-A, LO1-B Synthesizer EOVSA Prototype Review
LO Distribution Module Interior Layout EOVSA Prototype Review
LO Distribution Module Rear Panel EOVSA Prototype Review
Quinstar Power Amplifiers for LO1 EOVSA Prototype Review
LO Distribution Module Interface PCB EOVSA Prototype Review
LO Subsystem Design and Construction Current status • All components in, except 2.92mm cables. • Distribution module mechanical design complete, metal work on order. Assembly drawings delivered. • Need to generate detailed wiring diagram; mechanical assembly will begin ~ Oct. 1. • LO interface module under assembly, firmware development and GUI in progress. • Power supply module mechanical design and fab is TBD; DC power cable is ready. EOVSA Prototype Review
Timing Generation and Distribution Subsystem EOVSA Prototype Review
Timing & Reference Distribution Block Diagram EOVSA Prototype Review
Timing Generator Module Interior Layout EOVSA Prototype Review
Timing Generator Module Rear Panel EOVSA Prototype Review
1 PPS Driver, 50 Hz Generator PCB EOVSA Prototype Review
1PPS Laser Transmitter Unit EOVSA Prototype Review
EDFA / 16-way splitter (“PRD-16”) EOVSA Prototype Review
PRD-16 Rear Panel EOVSA Prototype Review
1PPS Optical Receiver EOVSA Prototype Review
Labview GUI for PRD-16 EOVSA Prototype Review
Timing Generation and Distribution Subsystem Design and Construction - Current status • All components are in. • TGD module mechanical design complete, metal work on order (fast turnaround) • Assembly drawing delivered. • Need to generate module wiring diagram; mechanical assembly will begin ~ Oct. 1. • Timing generator boards built, tested. • Will need a small additional PCB for output buffering of the optical RX, to correct polarity, pulse width and drive level for cRIO. EOVSA Prototype Review
Correlator Clock Generation (CCG) Module EOVSA Prototype Review
CCG Module Block Diagram EOVSA Prototype Review
CCG Module Interior layout EOVSA Prototype Review
CCG Module Rear Panel EOVSA Prototype Review
CCG Module Design and ConstructionCurrent status • All components in, except 1200 MHz PLO; expect it to ship 9/28/12 from vendor. • CCG module mechanical design complete, metal work on order (fast turnaround) • Assembly drawing delivered. • Need to generate CCG module wiring diagram; mechanical assembly will begin ~ Oct. 1. EOVSA Prototype Review
Rack-Level Design and Cabling EOVSA Prototype Review
Layout of Equipment Racks, Front View EOVSA Prototype Review
Partial Drawing of Analog Racks, Rear View EOVSA Prototype Review
LO Inter-rack Cable Routing EOVSA Prototype Review