1 / 63

Defence plan and System restoration

Defence plan and System restoration. Introduction. Inter-Connected operation - widespread propagation of disturbance Reliable defense plan essential Isolation or Islanding of Faulty portion to save rest of the system Load-Generation balance by UFR load-shedding required prior to islanding

jenny
Download Presentation

Defence plan and System restoration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Defence plan and System restoration NLDC

  2. Introduction • Inter-Connected operation - widespread propagation of disturbance • Reliable defense plan essential • Isolation or Islanding of Faulty portion to save rest of the system • Load-Generation balance by UFR load-shedding required prior to islanding • Consideration of large number of contingencies required for designing successful islanding schemes

  3. Common Sequence of events in blackouts System Separation Initiating Events Load /Generation Imbalance in islands Formation of Islands Begin Restoration Process Blackout of Islands

  4. Effect on Society • Production • Loss of productivity • Loss of product or property • Health • Food contamination • Medication problems • Anxiety • Safety • Traffic accidents • Accidents due to visibility problems • Civil unrest

  5. Public Scrutiny • Any widespread electric outage draws a lot of attention from: • Politicians • Governmental agencies • MOP • ERCs • Special interest groups • Consumer, Advocates, Environmentalists • Large customers • Media

  6. Types of Blackouts • Localized • Partial System • Full System With Outside Help • Full System Without Outside Help Restoration strategy may be different for each type of outage !

  7. Blackouts • System separations and blackouts are possible at all loading levels! • System separations and blackouts are possible at all times of the day and year! • Heavily stressed system is more likely to black out! • Prevention is the key to system restoration!

  8. Causes of Blackouts • Pre-disturbance conditions that could contribute to a system blackout: • Maintenance outages • Heavy/Uncontrolled loop flow through system • Changing generation patterns • Weather • Unexpected events/FAULTS • Relay mal-operation • Circuit breaker failure

  9. Causes of Blackouts • Cascading Thermal over loads • Voltage Instability • Dynamic Instability • Load Generation Imbalance Power Flow Thermal Limit Stability Limit Voltage Limit Load Total Transfer capability Time Horizon

  10. KV safe unsafe MW Causes of Blackouts • Voltage Collapse • Deficit of MVAR Supply • Over the “knee” of the voltage curve • Results in system separations and generation tripping

  11. KV safe unsafe MW Causes of Blackouts • Voltage Collapse • Difficult to predict boundaries of separation • May be detected by looking for areas of voltage decay • However, use of shunt capacitors can maintain near normal voltage up to the point where voltage support resources run out • Time Frame: minutes to tens of minutes Var Support

  12. Causes of Blackouts • Dynamic Instability • System does not damp out normal oscillations • Groups of generators “swing” against each other resulting in large oscillations in MW, MVAR. • Could result in: • Generation tripping • Voltage collapse • Equipment damage • Time Frame: 5 -15 seconds • Load Generation Imbalance • Insufficient generation w.r.t connected load • Insufficient spinning reserve • Low frequency leading to low voltage

  13. SYSTEM RESTORATION Last Blackout In WR: - Date: 30th July 2002 System Affected: Whole Region except parts of Mumbai (21,500 MW) Time of Disturbance: 20:11 / 30.07.2002 Time of Restoration : 06.00 / 31.07.2002

  14. SYSTEM RESTORATION Last Blackout In ER: - Date: 25th July 2000 System Affected: Whole Region (7,300 MW) Time of Disturbance: 21:10 / 25.07.2000 Time of Restoration : 07:00 / 26.07.2000

  15. SYSTEM RESTORATION Last Blackout In NR: - Date: 2nd January 2001 System Affected: Whole Region (19,800 MW) Time of Disturbance: 04:44 / 02.01.2001 Time of Restoration : 13:32 / 02.01.2001

  16. Defence Plan • Element Protection • Line Protection • Generator Protection • Transformer Protection • Relays to prevent cascade tripping • UFR • dF/ dT • Under Voltage • Islanding • System Islanding • Power Station Islanding • System Protection Schemes

  17. Defense Plan Ingredients • Defense plan need to be coordinated with planning, operations, and maintenance • Not intended to compensate for lack of other investments • Could help better utilize system margins, but as a last line of defense to improve system security and prevent disturbance propagation • Clear understanding of the requirements and consequences • Coordination with neighboring systems • High performance equipment • Emphasis on security vs. dependability • Real-time measurements and reliable communication • Planned & designed for future system and technology expansions

  18. Restoration Planning

  19. Objective • Extending start up/survival power to all the Thermal power plants and Synchronisingat least one unit at all power station • Restoring normal system operation as early as possible • Restoring essential loads • Establishing all interconnections • Minimizing amount of unserved energy • Starting contracted and economic despatch

  20. General Guidelines • FORMATION OF A PLANNING TEAM • PARTICIPATION OF EXPERIENCED/ KNOWLEDGEABLE PERSONNEL FROM RESPECTIVE FIELDS LIKE PROTECTION, COMMUNICATION, OPERATION, SYSTEM ANALYSIS ETC. • REVIEW OF SYSTEM CHARACTERISTICS (RELEVANT TO RESTORATION)

  21. Problems /Constraints • Impaired communications, limited information. • Non-availability of SCADA/EMS application system. • Unfamiliarity with the situation (does not occur regularly) • Non availability /breakdown of a critical element • Time constraints re-assembling tie elements of power system.

  22. Common Concerns • Time consuming nature of switching operation • Start-up timings of thermal units • Voltage problems during energisation of underloaded lines • Cold load inrush, power factors and coincident demand factors • Behaviour of protection system

  23. System Characteristics

  24. Structural • System size • Metropolitan or rural • Nature of generation distribution and its mix • Transmission voltage levels • Types and sizes of load blocks • Availability of Interconnection Assistance  

  25. Dynamics • Reactive capabilities of generators • Generator max and min output under different conditions • Shunt reactors and capacitor sizes and mode of control • Charging current and maximum sustainable overvoltage • Tap changers and modes of control • Synchronising facilities available other than generating stations • Fault MVA- during early stages of restoration

  26. Formulation of Assumptions • Wide variation of constraints under peak and lean condition • Start up of cycling steam units under lean condition (may not be necessarily applicable in Indian context) • Coordination of load pickup with generator response – essential to arrest dangerous decline of frequency particularly during peak condition. • Non-Availability of Black start facility during odd hours or during week ends. • Restricted Capacity of Hydro units during non-monsoon seasons.

  27. Strategies and Tactics

  28. Restoration Process • Bottom-up/Build-up Strategy • Steps involved in the “Bottom-up Strategy” • 1)Select units to black-start. • 2)Start and stabilize black-start units. • 3)Determine restoration transmission path. • 4)Begin expanding island(s) by restoring transmission and load. • 5)Synchronize island(s) when appropriate.

  29. Restoration Process • Restore backbone transmission system, usually from outside assistance. • Restore critical generating station and substation load from transmission system. • Bring on more generation. • Restore underlying transmission system. • Continue restoring load. Top-down / Build down strategy

  30. Combination Approach • Combines the “Build-up” and “Build-down” approach. • Steps in this approach include: • Restoring transmission from an outside source at the same time as building “islands” of generation. • Interconnecting “islands” with each other or outside source when able.

  31. Selection of Restoration Strategy • Restoration method chosen depends on: • Extent of blackout • Availability of outside assistance • Availability of internal black-start generation • Objectives of restoration • Utility philosophy/procedure

  32. Restoration Tasks

  33. Restoration Tasks • INITIAL ASSESSMENT • SYSTEM STATUS DETERMINATION • PLANT PREPARATION SERVICES/START-UP • NETWORK PREPARATION • NETWORK ENERGISATION • LOAD RESTORATION • SYSTEM REBUILDING

  34. Initial Assessment • SCADA/EMS Alarm • First indication of a problem • Barrage of alarms will appear • SCADA/EMS performance may be slowed due to amount of alarm processing. • Communication failures • RTU failure or substation battery failure • Data received may be of questionable integrity.

  35. Initial Assessment • Communications • Functional communications are critical • Assessment of the extent of a blackout. • Verify communication with • Control centers • Other Generating Stations • Substations • Verify backup communication systems • Eliminate non-productive telephone communications. • Call for help • Extra manpower

  36. System Status Determination • Extent of black out and actual requirement • Identification of boundaries of energised areas • Ascertaining frequency & voltage of energised area • Status of generating plants (hot/cold) • Equipment overloads and troubles • Loads interrupted by under- frequency relay operation or direct tripping

  37. Determining Generator Status Determine surviving on line Generation Stabilize surviving on line Generation Determine status of off-line generation Restore aux power to off-line generation Begin start-up of off-line black-start generation Determine optimum sequence of unit start-up

  38. Determining Generator Status • For generation that is still on-line determine: • Location • Damage • Stability • Frequency of island • Can load be added? • Unloaded capacity • Connectivity to the rest of the system • Islanded completely

  39. Determining Generator Status • For generation off-line determine: • Status prior to blackout • Black-start capability of unit • Unit type • individual unit characteristics • Damage assessment • On-site source of power available or is off-site source (cranking power) required • Availability and location of cranking power

  40. Determining Generator Status • Auxiliary power should be restored to generation stations as soon as possible. • Short delays in restoring auxiliary power could result in long delays in restoring generation

  41. Determining Generator Status • Prioritization of available cranking power to generation depends on: • Individual restoration plan • Start-up time of unit • Availability of on-site auxiliary power • Distance of cranking power from generation • Effective communication with Local Control Center is essential in this process!

  42. Determining Generator Status • Generating plant operators take actions to perform a safe plant shutdown. • Steam plant operators implement start-up procedures immediately following a plant shutdown unless instructed otherwise by the dispatcher. • Governors must be in service. • Plant operators must take action on their own • To control frequency outside the range of 49-50.5 Hz • To maintain coordination with appropriate load despatch centre under control

  43. Network Preparation • Clearing all de-energised buses • Global opening of all the breakers • Sectionalising a system into sub-systems to enable parallel restoration of islands • Under frequency relays may have to be kept out of service at the initial stage • Making provision of cranking power for generating units • Immediate resumption of power supply to the pumps meant for high pressure cable

  44. Reactive Power Balance • Energising EHV circuits or High voltage cable to be avoided as far as possible • Shunt reactor at the far end of the cable/EHV O/H line being energised to be taken into service first • Radial load to be put first • Global knowledge about the magnitude and location of reactive reserves of the system

  45. Load Restoration • Priority load for restoration • Generating Unit auxiliary power • Nuclear Station auxiliary power • Substation light and power • Traction Supplies • Supply to Collieries • Natural gas or oil supply facilities

  46. Start Up Power Supply to Traction • Ready availability of feeding points, transformer capacities, contract demands, phases used etc. details • 25kV network instead of 132kV system, for extension of power • Assistance from healthy feeding points in neighbouring regions • Judicious use of power (e.g. only passenger trains to be hauled to the nearest station) • No new trains to originate • SLDCs to check phase balancing to avoid negative sequence problems

  47. Load Restoration • Frequency Control • Maintain frequency between 49 and 50.5 Hz with an attempt to regulate toward 50 • Increase frequency to 50.00 -50.5Hz prior to restoring a block of load. • Manual load shedding may need to be done to keep the frequency above 49.50 • Shedding approximately 6-10% of the load to restore the frequency 1 Hz.

  48. Load Restoration • Frequency Control • Restore large blocks of load only if the system frequency can be maintained at 49.5 or higher • Restore load in small increments to minimize impact on frequency. • Do not restore blocks of load that exceed 5% of the total synchronized generating capability. • For example: If you have 1000 MW of generating capacity synchronized on the system, restore no more than 50 MW of load at one time.

  49. Island Interconnection • How do I know if my system is stable? • Voltage within limits • Small voltage deviations when restoring load or transmission • Frequency within 49.5 and 50 • Small frequency deviations when restoring load • Adequate reserves (spinning and dynamic)

  50. Island Interconnection • Synchronisation • Frequency and voltage of the smaller island should be adjusted to match the frequency and voltage of larger island • Frequency and voltage in a smaller system are able to be moved more easily with smaller generation shifts. • Failure to match frequency and voltage between the two areas can result in significant equipment damage and possible shut-down of one or both areas. • Post-synchronism • If possible, close any other available tie-lines between the two newly connected systems to strengthen stability • Larger company has more resources to control frequency • The larger Utility/Area will control frequency while the other will resort to tie-line control through appropriate demand/generation management.

More Related