RESITA HYDRO PROJECT CEZ GROUP

RESITA HYDRO PROJECT CEZ GROUP. ROMANIAN HYDRO POWER SUMMIT 2014. 20 February 2014. Semenic channel max 2,34mc/s. Safra channel. Timis Trei Ape pumping station, 834m a.s.l. Botosani. Baia Mare. Satu Mare. Suceava. Hbr=342m. Bistrita. Timis Trei Ape lake 4,4mio mc. Iasi. Zalau.

jill
Download Presentation

RESITA HYDRO PROJECT CEZ GROUP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RESITA HYDRO PROJECTCEZ GROUP ROMANIAN HYDRO POWER SUMMIT 2014 20 February 2014

  2. Semenic channel max 2,34mc/s Safra channel Timis Trei Ape pumping station, 834m a.s.l. • Botosani • Baia Mare • Satu Mare • Suceava Hbr=342m • Bistrita Timis Trei Ape lake 4,4mio mc • Iasi • Zalau • Oradea Hbr=474m • Piatra Neamt • Cluj-Napoca • TîrguMures • Vaslui • Bacau • MiercureaCiuc • Arad • Alba lulia • SfîntuGheorghe Main channel Gozna dam&lake (597m a.s.l.) 10,3 mio. mc • Timisoara • Deva HPP Crainicel 1, TWL=521m a.s.l. Pi=4,16MW, E-8,33GWh/year • Focsani • Sibiu • Brasov • Galati • Braila • Buzau Resita • RîmnicuVîlcea • Tulcea • TîrguJiu • Ploiesti • Pitesti • Tirgoviste • Drobeta-TurnuSeverin Valiug dam &lake 0,9 mio. mc • Slobozia Water pipes for Resita municipality • Slatina • Bucuresti • Craiova Birzava river • Calarasi • Constanta • Giurgiu Secu dam & lake, 300m a.s.l. 7,96mio. mc • Alexandria Grebla HHP, Hbr=215m, 249 m a.s.l. Pi=7,968MW, E=2854GWh/year Grebla pumping station HPP Breazova, Hbr=37m, 477m a.s.l. Pi=0,656MW, E=1,84GWh Project location and main parameters of Resita hydro system – refurbishment and modernization of 4 old hydro power plants Synoptic scheme of Resita water system Location: Romania, west part of country, Banat Region, CarasSeverin county 1012m a.s.l. Semenic water chamber, HWL=996m a.s.l TTA pumps (2x0,3mc/s) Safra water chamber, HWL=863m a.s.l Semenic river Barzava river Timis river Superior channel Breazova water chamber, 514m a.s.l. Rankina water chamber, HWL=464 m a.s.l. Hbr=37m Hbr=75m HPP Crainicel 2, TWL=521m a.s.l. 521m a.s.l. Pi=9,2MW, E=23,18GWh/year

  3. Refurbishment of old hydro system – main data for old technology • Resita project started with achievement from TMK Resita (steel factory), in 2010, of existing old hydro energetic system, in operation, located on the west part of Romania, on Semenic Mountains. The hydro system included mainly: • 4 hydropower plants (Grebla, Crainicel1, Crainicel 2 and Breazova); • 1 pumping station (TimisTrei Ape); • 4 dams/lakes: Gozna (10,27 millions mc), Secu(7,96 millions mc), Valiug (0,92million mc), TimisTrei Ape (4,4 millions mc); • 64km of channels, 12 tunnels and 4 main metallic aqueducts; • 32km of electrical networks 6kV and 35kV, 5 transformer stations MV/MV or MV/LV. • The energy generated in old HPPs it was used by steel factory using medium voltage network and substations; • The technology used in HPPs it was very old, the commissioning was as follows: HPP Grebla – 1970, HPP Crainicel 1 – 1956, HPP Crainicel 2 – 1997, HPP Breazova – 1950. • Old system included historical monuments, most important are the buildings(power houses) for HPP Grebla and HPP Breazova. • Total maximum power produced by the old equipment was around 18MW. HPP Grebla – old transformer station 6/35kV HPP Grebla – old equipment on machines room

  4. Refurbishment of old hydro system – images with old technology HPP Breazova – Power house (historical monument) HPP Crainicel 1 – Old machines room HPP Breazova– oldest Francis turbine, manufactured by GANZ in 1916 HPP Crainicel 2 – Old machines room

  5. Needed for refurbishment of small hydro power plants were coming as a result of the high degree of wear and tear of initial old equipment and risk for negative potential environmental impact. HPP Crainicel 1– Reinforcement steel and concrete pouring for foundation of new turbine and generator HPP Crainicel 2 – Works for foundation of new turbine, generator and anchor blocks HPP Breazova– Reinforcement steel and concrete pouring for foundation of new turbine and generator PS TTA – Desassembly of old technology

  6. Resita project – reconstruction in images • Refurbishment project was complex and was divided into eight major sections : HPP Grebla , HPP Crăinicel I, HPP Crăinicel II, HPP Breazova , Water channels, Pumping Station Timis Three Waters (TTA) , Transformer station 6/35/110 Grebla and OHL 35 kV OHL from hydro system and last one Connection to the national electrical distribution network 110 kV. • In May 2011 started the refurbishment project of old existing assets technology from Resita hydro system, which consist mainly in design and execution of the replacement of existing equipment with new ones, repairs of channels, aqueducts, electrical networks 35kV and new connection to the national electrical system, including main transformer station. The design and permitting stages were developed in 2011-2012 in parallel with the operation of old HPPs. • The hydropower plants were in operation till end of July 2012, when started the execution works, in parallel for sections HPPs, PS TimisTrei Ape and Channels. Electrical execution works started in March 2013. Grebla transformer station 6/35/110kV– Foundations reinforcement steel HPP Grebla– Installing of new technology

  7. Refurbishment – refurbishment in images • The refurbishment works are made base on fully yellow turn-key contract, signed by CEZ Romania with Hydropol; • The main stages of this project were:  Disassembly of old machines;  Carrying out construction works necessary for assembly of new equipment;  Installation of new equipment;  Testing and commissioning of new equipment. • Effectively execution of the work began in July 2012 based on Building Permits obtained, by disassembling old machinery. Complex tests started in October 2013 and first coupling of new generators were in November 2013. All new generators were ready for continuous operation in first part of December 2013, as it was planned. HPP Grebla – Penstocks and anchors blocks refurbishment HPP Grebla – Dispatcher control room

  8. Refurbishment of Resita hydro system – new technology in operation • The new equipment installed in the 4 small HHPs (Grebla, Crainicel I, Cranicel II and Breazova) meet high performance criteria and include turbines, generators and transformers, GIS module, electric cells and automation panels, automated equipment for water cleaning and were produced by companies with experience in domain from countries like Germany, Italy and Norway. • The general contractor of the work collaborated with Romanian companies throughout the project, supporting local economic development environment. Also, one of the major advantages of refurbishment for the community is the direct link to the National Energy System for Brebu Nou and Garana villages and reserve supply for the area Valiug - Semenic Mountain. • Following the commissioning of new equipment, total installed power in the 4 hydro power plants increased from 18 to 22MW and confirmed increased efficiency of production of hydro power (about 20%), and an improved level of environmental protection. • Al hydro system is leaded on SCADA from Grebla dispatching (control) room and from Craiova DED 110kV for local electrical grid. • End of refurbishment and modernization works was registered in December 2013 and fully commercial operation in January 2014 Grebla transformer station 6/35/110kV – connection with SEN HPP Grebla– Works finished

  9. Refurbishment of Resita hydro system – new equipment ready for operation HPP Crainicel 2 – New technology installed HPP Crainicel 1– Final stage of refurbishment Channels – New steel gates installed and channel refurbished HPP Breazova– New turbine and generator installed

  10. BACK - UP

  11. Refurbishment of Resita hydro system – technical parameters of HPPs *) Source: Hydropol CZ, General Contractor

  12. THANK YOU FOR YOUR ATTENTION!