AMD Decision to Locate in Luther Forest Technology Park. Quarterly Management Meeting September 13, 2006. Focusing Community Efforts Strategic Outreach Prospect Research Business Recruitment Energy Infrastructure Capital Investment Incentive Three Phase Power Incentive 25 Cycle Incentive

jirair
Download Presentation

AMD Decision to Locate in Luther Forest Technology Park

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AMD Decision to Locate in Luther Forest Technology Park Quarterly Management Meeting September 13, 2006

  2. Focusing Community Efforts Strategic Outreach Prospect Research Business Recruitment Energy Infrastructure Capital Investment Incentive Three Phase Power Incentive 25 Cycle Incentive Energy Efficiency Small Business Assistance Energy Efficiency in Empire Zones Dairy Industry Productivity Developing Sites Shovelready infrastructure Building ready Program Industrial Building Redevelopment Commercial District Revitalization Brownfield Redevelopment Courting Prospects Site Inspections and Area Tours Discount Programs Supplier and Distributor Network Market Research National Grid’s Economic Development efforts help customers invest in Upstate New York

  3. History

  4. Seven Years Leading up to Sematech

  5. The Albany NanoTech Complex of the UAlbany College of Nanoscale Science & Engineering

  6. Luther Forest Tech Park Saratoga Springs Site Location Albany

  7. Luther Forest Tech Park Site Layout Substation

  8. Routing of four 115kV lines and Station site have been roughly determined Malta National Grid Mulberry NYSEG

  9. AMD Dresden, Germany

  10. Impact