1 / 9

City of n Tigard

City of n Tigard. Respect and Care | Do the Right Thing | Get it Done. Active Capital Construction Projects. Presented to Tigard City Council March 22, 2011. Pacific Hwy/Greenburg Rd/Main St Intersection Improvements. Respect and Care | Do the Right Thing | Get it Done. Pre-construction.

joel-holden
Download Presentation

City of n Tigard

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. City ofn Tigard Respect and Care | Do the Right Thing | Get it Done Active Capital Construction Projects Presented to Tigard City Council March 22, 2011

  2. Pacific Hwy/Greenburg Rd/Main St Intersection Improvements Respect and Care | Do the Right Thing | Get it Done • Pre-construction

  3. Pacific Hwy/Greenburg Rd/Main St Intersection Improvements • Post-construction

  4. 550-foot Zone Improvements • 10-million gallon Transfer Pump Station • Piping installation connecting the reservoir to the pump station

  5. 550-foot Zone Improvements • 10-million gallon Transfer Pump Station • Forming, installing rebar, and adding conduit for the pump station

  6. 550-foot Zone Improvements • 10-million gallon Transfer Pump Station • Pouring the top of the pump station building

  7. 550-foot Zone Improvements • 10-million gallon Transfer Pump Station • Finished concrete surface top of the pump station building

  8. 550-foot Zone Improvements • 10-million gallon Transfer Pump Station • Painting the inside of the reservoir

  9. 550-foot Zone Improvements • 10-million gallon Transfer Pump Station • Building the footing for the architectural screen wall along Bull Mountain Road