1 / 12

APX Project Plan Kickoff: Milestones, Timeline, Organization & Communication

This project plan outlines contractual milestones, project timeline, deliverables, and organizational structure for the APX Project. It includes details on communication and contact plans, NEPOOL/NE-ISO personnel requirements, and REC System Test Drive. The plan also specifies key dates for deliverables and feedback, along with the project team's roles and responsibilities.

joeygreene
Download Presentation

APX Project Plan Kickoff: Milestones, Timeline, Organization & Communication

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. APX Project Plan Kickoff 6 November 2001

  2. Table of Contents • Contractual Milestones • Project Timeline • Project Deliverables • APX Project Organization • Communication/Contact Plan • NEPOOL & NE-ISO Personnel Requirements • REC System Test Drive

  3. Contractual Milestones

  4. Project Timeline - Phase 1

  5. Project Timeline - Phase 2/3

  6. Project Deliverables Delivery DateFeedback By • Bi-Weekly Status Report 1st - Nov 12, 2001 • Project Plan Nov 26, 2001 • Statement of Work Nov 26, 2001 Dec 3, 2001 • System Requirements Document Dec 10, 2001 Dec 17, 2001 • SDR Agenda Dec 31, 2001 Jan 10, 2002 • SDR Package Jan 8, 2002 • System Design Document Jan 14, 2002 Jan 24, 2002 • System Test Plan Jan 18, 2002 Jan 25, 2002 • Training Plan Mar 18, 2002 Apr 25, 2002 • System Test Report Mar 29, 2002 • Training Documentation Mar 29, 2002 • Operational Acceptance Test Report Apr 19, 2002

  7. APX Project Organization • Business/Site Manager – Gary Zielanski • Project Manager - Tom Hickey • System Requirements - Michael Rucker • Lead Engineer - Hung Chau • System Test Engineer – Charles Kominczak • Quality Assurance Lead – Roy Gvirtsman • Software Engineer - Welock Kam • Director, Information Technology - Mike Johnson

  8. APX Project Organization

  9. Communication/Contact Plan

  10. NEPOOL/NE-ISO Personnel Requirements Phase 1 – Definition & Design • Working Group Support • NEPOOL MSS Interface Design • Document Feedback • SRR & SDR Attendance & Involvement Phase 2 – Development • Working Group Support (As needed) • Document Feedback • Integration to the NEPOOL MSS Phase 3 – Training & Operations • Feedback on Training Documentation • Support for Training Logistics • Feedback on Training • Operational Acceptance Test Attendance & Involvement

  11. REC System Test Drive

  12. Test Drive The REC System http://testrec.apx.com/ Login Name = apx2 - apx250 Passwords = txrec

More Related