An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CREPC Meeting Ray Brush NorthWestern Energy April 20, 2005

  2. Open Season • Typical Open Season • Transmission Developer has Transmission Plan and seeks participants and/or parties to contract for capacity. • Northwestern Open Season • Interest in New Capacity in Montana- Southeast Idaho (AMPS). • Develop transmission additions to provide service for new capacity. • Allows consideration of multiple needs in one study. • Within the current FERC Process for Transmission Service Requests. • If works out will expand to other paths.

  3. Why Montana-Idaho Path (Path 18)? • RMATS Study • Recent RFPs for Resources (IPC and PAC-Utah) • SPP need for access to additional resources. • Resource development proposals in Montana. • Fewer Siting Issues • NWE’s Firm capacity in existing facilities fully committed.

  4. NorthWestern’s Open Season Process • Expression of Interest (EOI) • Open Season Capacity Request period • Not require deposit • System Impact Studies at NWE’s expense. • Current requests considered. • System Impact Study Results • Facilities Study • Deposit Required to continue • Facility Study Results • Contract for New Capacity

  5. Results to Date • EOI • 800 MW of new capacity • Open Season Capacity Request • About 2250 MW signed up for new capacity • System Impact Study • System Additions range from new 230 kV line up to a new 500 kV line.

  6. Open Season Benefits • Brings generators/suppliers/load serving entities together • Allows “preview” of system impacts prior to significant financial commitment • Potentially eliminates “lumpiness” in transmission planning and construction (Ex. 200 MW expansion that no single party can commit to) • All parties cooperate, including the transmission provider, to solve regionwide problem of “what comes first, transmission or generation”

  7. Questions and Comments