Maint. Dept. Quality Circle Project for Month of Oct.13

Maint. Dept. Quality Circle Project for Month of Oct.13. Treatment ladle Gear Box & Motor Safety Guard & Stand modification work. Responsibility- SRF Maint. Team. Total no. of TL = 11 a) TL for 550kg = 5 b) TL for 750kg = 5 c) Monorail Ladle = 2.

junius
Download Presentation

Maint. Dept. Quality Circle Project for Month of Oct.13

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maint. Dept.Quality Circle Project for Month of Oct.13

  2. Treatment ladle Gear Box & Motor Safety Guard & Stand modification work. Responsibility- SRF Maint. Team

  3. Total no. of TL = 11a) TL for 550kg = 5b) TL for 750kg = 5 c) Monorail Ladle = 2

  4. Total no. of TL without Safety Cover = 03a) TL for 550kg = 01b) TL for 750kg = 02

  5. TL without Safety Guard(550kg & 750kg) Motor with Chain & Chain Sprocket Gear Box

  6. Total no. of TL Need to replaced stand= 06a) TL for 550kg = 03b) TL for 750kg = 03

  7. TL stand Condition Faulty Stand. Extra modification required to avoid shifting.