1 / 35

Enhancing Infrastructure: Peanut Drive RCC Street Project

Learn about Pennsylvania's first liquid fuel-funded RCC street project in Conewago Township, Adams County. Discover the benefits, challenges, and quality assurance processes involved in this innovative project.

jwooding
Download Presentation

Enhancing Infrastructure: Peanut Drive RCC Street Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Peanut Drive (T-479):Pennsylvania’s First Liquid Fuel Funded RCC Street Project Conewago Township, Adams County, PA PennDOT Engineering District 8-0 Presentation courtesy of:

  2. Introductions Ken Justice, PE Senior Director, Local Paving (215) 540-9999 email: kjustice@nrmca.org

  3. NRMCA Local Paving: Technical & Promotion Personnel Brian Killingsworth, P.E.  Senior Vice President Division Head, Local Paving San Antonio, TX Glenn Ochsenreiter Senior Vice President, National Resources Silver Spring, MD Jon Hansen Senior Vice President, Local PavingPleasant Hill, IA Amanda Hult, P.E. Senior Director, Local PavingLebanon, TN Ken Justice, P.E.  Senior Director, Local Paving Ambler, PA Phil Kresge Vice President, Local PavingMacungie, PA Don Clem, P.E.  Vice President, Local Paving Denver, CO Julie Buffenbarger, FACI, LEED AP Senior Vice President, Local Paving Hinckley, OH

  4. Local Paving Division: State and Regional Assignments

  5. Peanut Drive RCC Street Project Conewago Township, Adams County, PA PennDOT Engineering District 8-0

  6. Peanut Drive RCC Street Project VIDEO https://www.youtube.com/watch?v=9Kc232FzADk

  7. Project Location

  8. Project Location PEANUT DRIVE

  9. Project Location

  10. Phase I Existing Conditions – Repaired in 2013

  11. Phase II Project Plans – Plan View 1,500 LF Total

  12. Phase II Project Plans – Plan View 1,500 LF Total

  13. Phase II Existing Conditions

  14. Phase I/II Project Plans – HMA Section 4” Mill 1- ½” Wearing Course 4” Binder Course 8” Aggregate Base Course

  15. Phase II Project Plans – RCC Section(s) 1- ½” Wearing Course 6” RCC Base 6”-8” Aggregate Base Course

  16. Phase II Construction - 2014

  17. Issues to Consider Funding 1. Durability 2. Utility Maintenance 3. 4. Traffic Volumes 5. Access During Curing Benefits & QA/QC 6.

  18. Issues to Consider Funding: Issues with Liquid Fuel • Not initially recognized for use in PennDOT-funded projects • Township mandated to use Liquid Fuels due to PIB loan requirements • Pilot Project approval required to advance on original schedule

  19. Issues to Consider Durability vs. Bituminous Hot Mix Asphalt (HMA) Roller Compacted Concrete (RCC)

  20. Issues to Consider Durability • Township Adopted Five-Year Road Master Plan to Fund Street Projects • Enhanced Design Life Appealed to Township • Provides Opportunity to Gain Ground on Road Conditions

  21. Issues to Consider Traffic Volumes • Peanut Drive • Low volume • Opportunities to consider eliminating HMA Wearing Course • Oxford Avenue • Future project high volume • Overall traffic heavy truck volume

  22. Issues to Consider Utility Maintenance • Township altering protocol for street cut restoration by utilities (after RCC) • Additional planning and longer lead times to upgrade and maintain utilities (ahead of RCC placement)

  23. Issues to Consider Access during Curing • HMA: soon as mat has cooled • RCC: recommended three day cure period

  24. Issues to Consider Benefits & QA/QC • Ability to bridge weaker (Karst) areas in Township • Contractor availability/qualifications

  25. PennDOT Pilot Project PennDOT Approval:9/19/2014 Project Start:10/16/2014 Project Complete:10/31/2014

  26. PennDOT Pilot Project Bi-annual reviews: distress assessment per Pub. 336 Reviews to occur on both Phase I and II sections Review to photo document conditions Updated traffic counts (at time of review) Field Evaluation Program

  27. PennDOT Pilot Project Verification of non-movement in subbase (Proof Roll) Nuclear Density Testing: dry density, % compaction and % moisture Compressive Strength: Six Cylinders Tested at 3, 7, and 28 days) Materials Testing Program

  28. PennDOT Pilot Project Nuclear Density Test Results

  29. PennDOT Pilot Project Initial Testing Results 28 7 3

  30. PennDOT Pilot Project Useful material to provide a durableroad section for municipalities Requires careful planning compared to HMA(access, utility, cost, and traffic volumes) May provide a more “stable” unit cost forlimited road budgets Shows impressive early strength results(potential to be a better long-term investment) Municipal Summary/Takeaways

  31. Did PennDOT like the use of RCC?

  32. Special thanks… Dan MoulPennsylvania State Representative (91st Legislative District) Bill HeapeConewago Enterprises, Inc. Mike KeiserPennDOT District 8-0 Gary TiptonPennDOT Municipal Services Conewago Township Board & Staff

  33. Kenneth Justice P.E. Senior Director – Local Paving kjustice@nrmca.org 267-716-8675

  34. Questions?? QUESTIONS???

More Related