An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CPS LOCAL EXCHANGE CALLSBT WHOLESALE UPDATE2 SEPTEMBER 2004 TIM HOWSONPRODUCT DEVELOPMENT MANAGER The information in this presentation does not form part of a contract

  2. AGENDA BACKGROUND PROJECT TIMELINE FULL SOLUTION INTERIM SOLUTION

  3. BACKGROUND • CPS design recognised from inception as inefficient for same exchange calls (tromboning). • Ofcom Statement published 30th July 2004: • BT now asked to keep these calls “on-net” and bill CPSO accordingly. • Dependent on CPSO build-out to DLE • New Product Variant – “CPS Local Exchange Calls” • New Industry Working Group established – Same/Adjacent DLE IWG

  4. BACKGROUND Own localexchange calls Adjacent connectedlocal exchange calls Call routingused byBT Retail BT DLE BT DLE BT DLE Call routing used by fully interconnectedCPSO BT DLE BT DLE BT DLE CPSOSwitch CPSOSwitch

  5. PROJECT TIMELINE 2005 100% Contract & DMA Dates tbc 75% AXE 10 Activation18 Mar – 31 Mar* 35%lines 50% System X MainActivation1 Apr – 30 April* 92%lines 25% System X Residual Activation2 May – 31 Oct* 100%lines 0% EBCCycle1 Jan EBCCycle1 Apr EBCCycle1 Jul EBCCycle1 Oct EBCCycle1 Jan * These are planned dates

  6. FULL SOLUTION • Two Main phases plus one “Mop-Up” Phase • BT will be discussing new contract with SAD IWG late October • CPSO’s will need to “opt-in” to full solution on per DLE, per CPS Code basis. • Revised DMA process and timescales to be offered for this “on-boarding” • CDRs to be made available for fraud prevention and billing purposes, c.f. Wholesale Calls & Wholesale Access

  7. INTERIM SOLUTION • BT has identified those CPS calls over DLE interconnects that would qualify for the new product variant. • BT will be issuing credit notes against same/adjacent connected DLE calls meeting above criteria – against the cost disadvantage as seen by Ofcom. • Credit notes will be issued monthly from September, backdated to 1 July 2004. • Interim Solution will continue until CPSO takes full solution on particular DLE under roll-out plan. • BT has published an amendment to the Carrier Price List and issued a briefing to explain this in more detail.