An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Workshop on appraisal of disassembled magnetsLesson learntMarch 17th, 2005 Inventory of cases F. Savary

  2. Inventory of cases • Quench failure • To date, 8 magnets have been dismounted (plus the case of 1005 with the cold weld): • 1026, 1126 and 1143 • 2013, 2023 and 2069 • 3136 and 3224 • There are other cases which are still pending (these magnets are still at CERN ready to be sent back to the CMA or already there waiting for repair or action) • 2024 (similar to 2025), 2098, 3208, 3220 (a 3rd run has been requested) • Special cases • 2025, which has been retested “as is” with two additional runs • 3219 and 3278, which have been submit to a third run • There is also a firm 1 case, which has seen a third run incidentally Inventory of cases - FS

  3. Inventory of cases, cont’d • Electrical failure: quench heater to ground and/or quench heater to coil, quench heater interruption • To date, 3 magnets have been dismounted (plus the cases of 2002 and 3003) • 2049 • 3143 and 3234 • Other cases are still pending (these magnets are still at CERN ready to be sent back to the CMA premises or already there waiting for repair) • 2124, 2143, 3153, 3297 (still on the test bench) • Electrical failure: inter-turn shorts • To date, one magnet has been dismounted (plus the case of 3004): • 2032 Inventory of cases - FS

  4. Inventory of cases, cont’d • Electrical failure: wiring to ground at the level of the IFS box • 1019 Inventory of cases - FS

  5. Inventory of casesThose intercepted at earlier stages • There are other interesting cases of inter-turn shorts intercepted at the factory during the production, at the collared coils stage. These have been detected by electrical insulation tests on the c.c. under pressure in the collaring-press. Then, the localization of the defect has been possible thanks to ad’hoc analysis of the warm magnetic measurements • To date, 13 cases have been observed • 1103, 1105, 1111, 1124, 1127, 1141, 1146, 1154, 1165, 1178 (all having short on the connection side) and 1217 (having short on the non connection side) • 2087 and 2101 (both having short on the connection side) • There is also a series of q.h. failures intercepted at the factory thanks to HV tests and/or resistance measurements Inventory of cases - FS