1. 1 Mount Ararat Baptist Church Building Phase 1
Building Committee
Evaluation and Plan of Action
2. 2 Building Committee Position Tasked:
To build Phase 1, as defined by Strategic Task Force and outlined by Architect.
Authorized:
$11.7M by church for this task
$7.2M (loan) + $4.5M (RBO)
Reality:
Actual Phase 1 building costs and all furnishings estimated to be $22.7M
Options/Alternatives evaluated given fiscal constraints
3. 3 Reasons for Cost Increase Incorrect square foot cost estimate
Additional square footage
Construction material cost escalations (recent hurricanes and other natural disasters):
steel (structural, concrete reinforcing, and ductwork)
gas (petroleum base products)
gypsum
copper
concrete
Construction Labor increases due to USA immigration issues
4. 4 Fiscal Options Build all of Phase 1
$22.7M
Build Scaled Down Phase 1 (detailed later in brief)
Option 1: $18M
Option 2: $15M
5. 5 Phase 1 Cost
$22.7M
What:
All Site Work ground work, parking, etc
1400 Seat Sanctuary
Education Building
People Street
New Expanded Kitchen
Noahs Café
All spaces completely furnished
8. 8 Option 1 Cost:
$18M
What:
All Site Work ground work, parking, etc
1400 Seat Sanctuary
Reduced Education Building
People Street
Reduced Kitchen (Maintain function of current kitchen)
Noahs Café
11. 11 Option 2 Cost:
$15M
What:
All Site Work ground work, parking, etc
Roughed in space for 1400 Seat Sanctuary
Building Footprint only, not usable space
Reduced Education Building with roughed in footprint
People Street
Reduced Kitchen (Maintain function of current kitchen)
Noahs Café space only
14. 14 Building Committee Plan of Action Continue work with Architect, Consultants and Contractors
Continue seeking Stafford County Permit approvals
Develop and award $11.7M construction contract to proceed with phase 1 building plan working towards option 2 ($15M)
Contract options to be authorized when monies are available
Additional monies must be made available internally (Donations)
15. 15 February - April Major Milestones
Complete BZA process
Complete Wetlands Determination/Submission
Complete Conditional Use Permit
Complete Pre-construction activities and Value Engineering
Complete rerouting of utilities to accommodate new building construction
Complete and submit Construction Plans
Align Cost Estimate with RBO giving, available funds and bank loan
Establish Agreement with General Contractor
Key Personnel/Organizations
Architect (Rardin and Carroll Architects)
Pre-Construction Services (Jack Bays Inc)
Lawyer (Clark Leming)
Stafford County Administrators
Church Body (RBO participants and general giving)
16. June - October Major Milestones
Receive all relevant permits for site and construction work from Stafford County
Break ground for site work
Begin building construction
Manage building costs with available resources
Key Personnel/Organizations
General Contractor (Jack Bays Inc)
Stafford County Administrators
Church Body (RBO participants and general giving)
17. 17