Contractor EHS Performance Data. May, 2014. End Car Light on Train. data review. Contractor injuries year to date- 3 Dow Injuries year to date- 2 Contractor OSHA rate year to date- 0.17 Site OSHA rate year to date- .14. 2014 Dow/Contractor Injuries.

karim
Download Presentation

Contractor EHS Performance Data

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contractor EHS Performance Data May, 2014

  2. End Car Light on Train

  3. data review

  4. Contractor injuries year to date- 3 Dow Injuries year to date- 2 Contractor OSHA rate year to date- 0.17 Site OSHA rate year to date- .14

  5. 2014 Dow/Contractor Injuries Jan- logistics platform collapse Dow Jan- EOB slip trip and fall Dow Jan- Chemical exposure Contractor- BTT Feb- Slipped off pipe Contractor- D&W Feb 14- hand injury Contractor- BME March- ZERO! April- ZERO! 84 days since last recordable injury

  6. Job site hazards Address thru STAC card or during permitting process. - WALKING

  7. No hand injuries in April!

  8. No repeater injuries in April

  9. 2 Precautionaries and 3 First Aids in April

  10. Observation Participation

  11. Recognition

  12. Date of Recognition: 5-03-2014 • Company: Miken Specialties • Workers Name (s): Jimbo Turner - Foreman, R. Guerrero - Lead man, J. Moreno, E. Chavez, S. Ford, and G. Elizondo. • Work Location: A-3600 PMDI • Description of Recognition: I just wanted to thank Miken Scaffolding for a job well done on the PMDI T/A on nights. The night crew that worked here did an excellent job. They communicated very well and worked safely throughout the entirety of the turnaround. The foreman and the lead man were very professional and made a couple of calls that saved the T/A team money and valuable time. • Recognized By:Brett Bowers

  13. SWP Work Permit and You

  14. REMINDERS • NEXT Safety Contact meeting • 6/12/14