PROJECT PROFILE. MAPEX INFRASTRUCTURE PVT. LTD. PANAGARH- PALSIT SECTION OF NH 2. (Km 520.103 TO Km 584.929). The Project:. Organization Structure:_______________ “INSTITUTIONAL”. PROJECT ADMINISTRATION:-______. NHAI :-
E N D
PROJECT PROFILE MAPEX INFRASTRUCTURE PVT. LTD. PANAGARH- PALSIT SECTION OF NH 2 (Km 520.103 TO Km 584.929)
PROJECT ADMINISTRATION:-______ • NHAI:- The National Highway Authority of India, a statutory body constituted under the provisions of the National Highway Authority of India, Act, 1988 and having it’s principle office at Plot No. G-5 & G-6, Sector 10, Dwaraka, New Delhi 110 045, hereinafter referred to as NHAI. ●Concessionaire: Mapex Infrastructure Pvt. Ltd.:- M/s. Mapex Infrastructure Private Limited, a company incorporated under the provisions of the Companies Act, 1956, having its registered office Arihant Building, 2nd Floor, 53A, MirzaGhalib Street, Kolkata-700 016, West Bengal, India. hereinafter referred to as the “Concessionaire”
EPC Contractor : GAMUDA-WCT :- Gamuda-WCT Private Limited, a company incorporated in Republic of Mauritius under Companies Act, 1984. Registered office :- Arihant Building, 2nd Floor, 53A, MirzaGhalib Street, Kolkata-700 016, West Bengal, India • Independent Engineer: Unihorn India Pvt. Ltd. Project Office :- C/o, Bankim Timber Works (AmarSwapna), Opposite of Jaguar Shop, Near Purvasha Bus Terminal, Alisha, G. T. Road, Post - Joteram, Burdwan - 713 101, West Bengal
SALIENT MILESTONES:_______________ • Project Implementation Period : • Starting Date: 21.11.2001 • Completion Date: 09.06.2005 • Operation & Maintenance Period: • Starting Date: 10.06.2005
SALIENT FEATURES:_________________ • Minor Bridges : 5 • ROB : 1 ( Span- 496.917 m) • Underpass : 14 • Culverts : 64 • Interchanges : 1 • Signalized Junction : 2 • Grade Separator: 1
OPERATION AND MAINTENANCE FOR THE PROPOSED HIGHWAY:____________________ • The 15 years operation and maintenance of the project consists of: • Periodic maintenance • Routine maintenance • Periodic maintenance have been provided during 5th year, 10th year and 15th year from commercial operation date. • Routine maintenance works are standard and is generally expected to follow the operational and performance criteria as specified in relevant IRC/MORTH standards and specification.
PROJECT ASSETS AND FACILITIES:____ • Maintenance Yard (Km. 531+196) • Wayside Amenity (Km. 531+757) • Truck-Lay-Bye (Km. 557+895) • Gobinda Setu (Km. 563+119) • Grade Separator SH-7 (Km. 566+221) • Shaktigarh ROB (Km. 581+718) • PIU Complex (Km. 584+926) • Palsit Interchange (Km. 584+696)