Beam diagnostics control for J-PARC LINAC

Beam diagnostics control for J-PARC LINAC. Guobao SHEN J-PARC Center Japan Atomic Energy Agency Mar. 2008. Content. Overview of J-PARC LINAC IOC Development OPI Presentation Beam Observation Performance Summary. 1. Overview of J-PARC LINAC. Major Parameters

kasie
Download Presentation

Beam diagnostics control for J-PARC LINAC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beam diagnostics control for J-PARC LINAC Guobao SHEN J-PARC CenterJapan Atomic Energy Agency Mar. 2008

  2. Content • Overview of J-PARC LINAC • IOC Development • OPI Presentation • Beam Observation • Performance • Summary Beam diagnostics control for J-PARC LINAC

  3. 1. Overview of J-PARC LINAC • Major Parameters • Particles: H- (negative hydrogen) • Energy: 181 MeV, The last two SDTLs are debunchers (400 MeV for ACS, 600 MeV for SCL) • Peak current: 30 mA (50 mAfor 1MW at 3GeV) • Repetition: 25 Hz (additional 25 Hz for ADS application) • Pulse width: 0.5 msec L3BT 181(191)MeV (400MeV) (600MeV ) Beam diagnostics control for J-PARC LINAC

  4. 1. Overview of J-PARC LINAC • Beam diagnostics Beam diagnostics control for J-PARC LINAC

  5. 2. IOC Development • Hardware Interfaces of Monitor Control • WE modules from Yokogawa • Digitizer module for data acquisition • WE7118: 100MS/s, 14-bit resolution, 2 channels • for BPM, FCT & WSM • WE7111: 100MS/s, 8-bit resolution, 1 channel • for SCT and BLM • Digital switcher for phase detector • WE7262: DIO module • WER modules • Home-made Wave-Endless-Recorder. • 200MS/s, 12-bit resolution, 4 channels • for BPM • 10MS/s, 12-bit resolution, 4 channels • for BLM Beam diagnostics control for J-PARC LINAC

  6. 2. IOC Development • IOC for WE control • DAQ: • By IOC directly • IOC: • H/W: Advme7501 VME-SBC (PowerPC) • S/W: OS: vxWorks 5.5.1; EPICS: 3.14.8.2 Beam diagnostics control for J-PARC LINAC

  7. 2. IOC Development • IOC for WER control • DAQ: • Rack-mountedServer: A Java based Application (METIS) • IOC: • H/W: Rack-mounted Server (Intel-based) • S/W: OS: RHEL 4 (Nahant); EPICS: 3.14.9 Beam diagnostics control for J-PARC LINAC

  8. 3. OPI Presentation • Beam current • SCT waveform • MEDM based • Confirmed beam 1st day of 1st beam study • Beam current • EDM based • High intensity beam studyConfirmed beam @ 25mA Beam diagnostics control for J-PARC LINAC

  9. 30º dump SCT Bendmagnets 0º dump beam SCT Waveform 2mA 40s 3. OPI Presentation • Beam delivery • 1st beam observation at 30º dump (RUN3 ) • 181MeV, 5.5mA, 20μs, 2.5Hz Beam diagnostics control for J-PARC LINAC

  10. 3. OPI Presentation • Beam position • 181MeV, 25mA on May, 2007 • Waveform (MEDM) • Orbit (JCE Based) JCE: J-PARC Commissioning Environment Beam diagnostics control for J-PARC LINAC

  11. 4. Beam Observation BPM Monitor: Beam Position Stability SDTL03AX SDTL02BX May 24 Good position stability up to the SDTL-2 was performed, but positions were moving after the SDTL-3 in 0.5-1 hour cycle. We suspected a Q-magnet rare short, higher order mode in the cavity, etc., for this instability. Beam diagnostics control for J-PARC LINAC

  12. 4. Beam Observation Reason: The frame of the wire scanner is made of ceramics. Electrons from the cavity charge up the frame, and induced voltage steers the beam. Beam diagnostics control for J-PARC LINAC

  13. 4. Beam Observation BPM Monitor: Beam Position Stability September 29 SDTL05A After making new frame of the wire scanner, a clear beam orbit jump was not seen. Beam diagnostics control for J-PARC LINAC

  14. 4. Beam Observation BPM Monitor: Beam position jitter RUN12 Vertical Horizontal Last 2 BPM’s in L3BT injection line Last 2 BPM’s in L3BT injection line 2nd last BPM 2nd last BPM Last BPM Last BPM These 2 BPM’s are 4.1 m apart. The position jitter at the RCS injection is around ±0.2 mm (60 m in RMS) including the intrinsic jitter (or noise) of the monitor system. Beam diagnostics control for J-PARC LINAC

  15. Wire Scanner: Typical horizontal profile 4. Beam Observation 25mA Collimator section WS55 WS53 Slight haloobserved in the horizontal direction. WS59 WS57 Slight halo Noisy Beam diagnostics control for J-PARC LINAC

  16. 4. Beam Observation Wire Scanner: Typical horizontal profile 25mA Collimator section WS55 WS53 More profound halo is observed in the vertical direction. WS59 WS57 Noisy Beam diagnostics control for J-PARC LINAC

  17. 5. IOC Performance • Resource using ratio (repetition: 2.5Hz) • CPU usage: < 40% • Memory usage: ~ 25% • Performance • Repetition rate: up to 6Hz • Satisfy current requirement of beam commissioning (2.5~5Hz) • Achieved WE hardware limit During Beam commissioning CPU Usage Memory Usage Beam diagnostics control for J-PARC LINAC

  18. 6. Summary • Beam Diagnostics Control for J-PARC LINAC • Two type hardware interfaces are employed • Commercial hardware: WE from Yokogawa • Module based, Compact digitizer • Home-made digitizer: WER • EPICS based • IOC: • EPICS R3.14.8.2+vxWorks5.5.1 • EPICS R3.14.9+RHEL 4 • OPI • MEDM, EDM, JCE App • Effective beam commissioning • with the support of diagnostics control • The control of beam diagnostics proved their usefulness in the beam status observation, and the beam commissioning Beam diagnostics control for J-PARC LINAC