WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC). Albuquerque March 6 & 7, 2008. Major Topics. 2008 Spring Study Results -- California / Mexico Subregion -- Northwest Subregion -- Southwest Subregion -- Rocky Mountain Subregion MIC issues.
E N D
WECCMIC MeetingReport on Operating Transfer CapabilityPolicy Committee (OTCPC) Albuquerque March 6 & 7, 2008
Major Topics • 2008 Spring Study Results -- California / Mexico Subregion -- Northwest Subregion -- Southwest Subregion -- Rocky Mountain Subregion • MIC issues
California / Mexico Subregion – Spring 2008 The increase in SCIT is mainly due to the new Miguel – Sycamore #2 230 kV line, which came in service late 2006, the new Miguel – Old Town 230 kV line, and 2x63 MVAr shunt capacitors at Miguel 230 kV.
Northwest Subregion - Spring 2008 cont. *SOL Studies were performed for the operating season
Rocky Mountain Subregion – Spring 2008 WITH NUCLA AT 80 MW AND SW COLO LOAD 100 MW ** Miracle Mile-Laramie and Beaver Creek-Hoyt Construction Outages *** Snowy Range-Cheyenne Construction Outages
Implementation Time Schedule • These limits apply to the 2008 spring operating season starting April 1, 2008, and ending no later than May 31, 2008 pending completion of: • The Operating Procedures Review Group’s acceptance of the associated winter operating procedures for each of the interties and those operating procedures (including system monitoring and curtailment responsibilities) being implemented, and • Operating training and direction required to ensure operation within the established operating limits.