Program Management Using MS Project Server 2003. Frank Douvry PMP. Agenda. Program Management problem Old Solution New Solution Inter-project Dependencies Old Solution New Solution. Program Management Problem. How do you manage a program? Many projects What visibility do you need
E N D
Program Management Using MS Project Server 2003 Frank Douvry PMP
Agenda • Program Management problem • Old Solution • New Solution • Inter-project Dependencies • Old Solution • New Solution
Program Management Problem • How do you manage a program? • Many projects • What visibility do you need • Allow project managers some dignity • Track Key Milestones • Track Key Issues and Risks
Old Solution • Master Project • Insert all projects into one • Manage the Master project • Coordinate updates to projects • Allowed program manager a view of entire program • Cumbersome to manage
New Solution • Program Schedule • Identify the Key Milestones • Create a program level schedule containing only those milestones • Make project milestones dependencies • Does not duplicate resources • Only managing Key Milestones • Any changes at project level are reflected
Program Schedule View • Key milestones only • Save the schedule
Program Schedule View • Create Master project and insert program schedule
Program Schedule View • Insert other schedules as well
Program Schedule View • Show links being made
Program Schedule View • Show view of program schedule with links
Program Schedule Save • Save program schedules • Save individual schedules • DO NOT SAVE MASTER SCHEDULE
Program Schedule View • Show Baseline view with variance
Program Schedule View • Show Baseline view with variance
Program Schedule Issue View • Show Issues at program schedule level • Discuss having to input all information again
Program Schedule Issue View • Show how to get link information from original issue
Program Schedule Issue View • Show new program issue with link
New Solution Wrap-up • Program Schedule • Does not duplicate resources • Only managing Key Milestones • Any changes at project level are reflected • Issues do not have to be re entered
Inter-project Dependency Problem • Tasks from one project dependent on tasks in another • Need to know when things change
Old Solution • Inter-project Links • Hard to manage • Circular Links • Program manager out of the communication • All projects in link need to open
New Solution • Give Get schedule • Manages all inter-project dependencies • Visible at the Program level • Allows quick identification of circular references • Reduces project opens
Project 1 View • Identify milestone/task that is successor of task in another project
Give/Get View • Show schedule with get milestone/give milestone and link
New Solution Wrap-up • Give Get schedule • Manages all inter-project dependencies • Visible at the Program level • Allows quick identification of circular references • Reduces project opens