Operations • Problems and failures • Work in progress • Work completed • Problem reporting • Safety • New facilities
Problems and Failures Telescopes • Actuator cylinder leaks • Drive motor bearings • Rotator PWM drive amp, motor, servo • Mirror cover drives • M1 mirror thermal control (mixing valve) • Hard Point leaks • Wide field collimation
Work in Progress • Telescopes • Actuator leak repair • New actuator control cards • New PWM amps on rotators • Guider normalization, wiring, PLA’s, IMS drives, • M1 thermal control mixing valves • M1 Mirror cover drives, new bushings
Problems and Failures Enclosures • Shutter structure Clay • Enclosure jib cranes • UPS batteries • Louver seals • Wind Screen & Moon Roof drives • Rotating interface seal
Work in Progress • Enclosures • Louver seals • Rotating interface seals • Windscreen & Moon roof drives • Rotating seal (Baade) • Louver position encoders limits • Power line slip ring modems
Work In Progress • Software • M3 Tip-Tilt automation • Code normalization, ini files • Translate Fortran to C++ (enclosure) • Windscreen & Moon roof automation • EDS query tools • PWM Amps, Rotator guiding, servos • M1 thermo control servo
Work completed • Iodine cell actuator (Clay), ADC (MIKE) actuator and guider (#6) installed and tested • New rotating enclosure seal (Clay) • New jib crane limit switches (both enclosures) • New flat field lamp supplies and software • Aluminized M1 and M3 mirrors Baade • Washed M1 and M3 mirrors Clay • Clay shutter drive U-joint replacement • New Az & El drive bearings Clay
Problem reporting • Gnats problem tracking software installed locally. This is now our only problem tracking system • Telescope reports for night time problems and comments • Forums are used to transfer information and changes
Safety • Safety review by ACHS • Fire detection system was inspected and serviced • Fire extinguishers serviced • New policies on equipment operations, licenses required for all equipment, classes, training and licensing in progress • Road maintenance in progress • Poly-clinic inventory & supplies.
New Dormitory and Infrastructure • Conversion of Nagoya control room • Architecture review complete and contract in place • Construction crews on site • Completion ~June • Kitchen renovation programmed for May