Emerging Technologies Working Group Update to WMS

Emerging Technologies Working Group Update to WMS. Contents Update on NPRR 615 Update on PVGR Forecasting RFP Next ETWG Meeting. August 06, 2014. I. Update on NPRR 615. July 31 st TAC Meeting Agenda: http :// www.ercot.com/calendar/2014/07/20140731-TAC

kineta
Download Presentation

Emerging Technologies Working Group Update to WMS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Emerging Technologies Working GroupUpdate to WMS Contents Update on NPRR 615 Update on PVGR Forecasting RFP Next ETWG Meeting August 06, 2014

  2. I. Update on NPRR 615 • July 31st TAC Meeting • Agenda: • http://www.ercot.com/calendar/2014/07/20140731-TAC • On 7/31/14, TAC voted to recommend approval of NPRR 615 as recommended by PRS in the 7/17/14 PRS Report • Will likely be on next week’s BoD Agenda (12AUG)

  3. II. Update on PVGR Forecasting RFP SEE PVGR RFP DOCUMENT • RFP Released on July 16th • http://www.ercot.com/about/procurement/rfp/index • 9 – 10 Vendors submitted Notice of Intent to Propose • Proposals are due by August 18th • Anticipated Contract Award by December 1st • “The objective of this RFP is to allow ERCOT to produce accurate and reliable forecasts of PVGRs to be used as an input into the Day-Ahead Reliability Unit Commitment (DRUC) and Hour-Ahead Reliability Unit Commitment (HRUC) and to provide ERCOT a look-ahead capability to maintain a satisfactory level of reliability.”

  4. II. Update on PVGR Forecasting RFP From the RFP: Figure 1 – Data Flow and Dependencies of Renewable Production (PVGR) Potential Forecast

  5. II. Next ETWG Meeting August 27th • Updates on responses received for PVGR RFP • Other items, TBD

  6. APPENDICES

  7. Requested WMS Motion