Executive Session Director’s CD-2/3a Review of the MicroBooNE Project. July 12-14, 2011 Ed Temple. Agenda for Exec Session. Charge to Review Team Review Agenda Reviewer Writing Assignments DOE O 413.3 Critical Decision Tables Document Requirements
E N D
Executive Session Director’s CD-2/3a Review of the MicroBooNE Project July 12-14, 2011 Ed Temple
Agenda for Exec Session • Charge to Review Team • Review Agenda • Reviewer Writing Assignments • DOE O 413.3 Critical Decision Tables • Document Requirements • Breakout Review Assignments and Guidance • Project Cost – Management Reserve/Contingency Table • Cost/Schedule Review Guidance • Reporting Structure • Discussion Director's CD-2/3a Review of the MicroBooNE Project
Charge Director's CD-2/3a Review of the MicroBooNE Project
Charge (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Charge (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Charge (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Typical CD-2/3a Questions Director's CD-2/3a Review of the MicroBooNE Project
Typical CD-2/3a Questions (continued) Director's CD-2/3a Review of the MicroBooNE Project
Typical CD-2/3a Questions (continued) Director's CD-2/3a Review of the MicroBooNE Project
Agenda Director's CD-2/3a Review of the MicroBooNE Project
Agenda continued Director's CD-2/3a Review of the MicroBooNE Project
Agenda continued Director's CD-2/3a Review of the MicroBooNE Project
Agenda continued Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Writing Assignments Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Writing Assignments (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Writing Assignments (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Writing Assignments (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Summary of Major Requirements Table Director's CD-2/3a Review of the MicroBooNE Project
CD-2 Requirements Director's CD-2/3a Review of the MicroBooNE Project
CD-3 Requirements Director's CD-2/3a Review of the MicroBooNE Project
CD-2/3a Documentation • Acquisition Strategy • Final Project Execution Plan (PEP) • Final Project Management Plan (PMP) • Updated Assumptions Document • Technical Design Report (TDR) • Final Design Requirements for Long Lead Procurements (CD-3a Items) • Baseline Cost & Schedule and • Resource Loaded Schedule and Bases of Estimate (BOEs) • Configuration Management Plan • Preliminary Hazard Analysis Report • Risk Management Plan, Risk Register, Risk Assessment, Risk Mitigation Plans • Value Management Documentation • Quality Assurance Plan Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Breakout Assignments Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Breakout Assignments (continued) Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Breakout Assignments (continued) Director's CD-2/3a Review of the MicroBooNE Project
Breakout Session Focus • Subproject Risks • Have the risks been identified, analyzed, and mitigation plans & costs been established • Has the L2 been involved in the process and own their risks • Subproject Schedule • Do the L2s know and own their part of the schedule and own it • Is the schedule realistic for the scope of work • Do the L2s know the critical path for their work and where they are at related to the project’s critical path Director's CD-2/3a Review of the MicroBooNE Project
Breakout Session Focus (continued) • Subproject Costs • Are there BOEs for the entire scope of the subproject and do the estimates appear to be realistic and achievable • Has cost estimate uncertainty been developed and appropriate for the scope of work and phase of the project • Long Lead Procurements (CD-3a list) – Sessions 1 • Do final design specifications/requirements/drawings exist • Are packages prepared to the degree appropriate to order materials and initiate construction as scheduled Director's CD-2/3a Review of the MicroBooNE Project
Breakout Session Focus (continued) • Progressing /Reporting /Change Control • Is monthly progress reporting performed and what is the process • Does the process include schedule updates and a narrative description of progress • Does the L2s understand their role in the change control process and what is currently being used Director's CD-2/3a Review of the MicroBooNE Project
Project’s Cost Estimate Details Director's CD-2/3a Review of the MicroBooNE Project
Cost/Schedule Review Guidance Director's CD-2/3a Review of the MicroBooNE Project
Cost/Schedule Review Guidance (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Cost/Schedule Review Guidance (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Cost/Schedule Review Guidance (Continued) Director's CD-2/3a Review of the MicroBooNE Project
Reporting Structure • Results of the review are to be documented as findings, comments, and recommendations. • Answer the charge questions. Answers should be short and precise. • Any additional actions required to be completed by the project team to acceptably address the review charge are to be documented as Recommendations • Answers to the questions and any recommendations should be presented in writing at a closeout with MicroBooNE’s and Fermilab’s management. • . Director's CD-2/3a Review of the MicroBooNE Project
Findings, Comments, and Recommendations • Findings • Comments • Recommendations • Findings are statements of fact that summarize noteworthy information presented during the review. • Comments are judgment statements about the facts presented during the review. The reviewers' comments are based on their experiences and expertise. • The comments are to be evaluated by the project team and actions taken as deemed appropriate. • Recommendations are statements of actions that should be addressed by the project team. • A response to the recommendation is expected and that the actions taken would be reported on during future reviews. Director's CD-2/3a Review of the MicroBooNE Project
Examples of Findings, Comments, and Recommendations Finding • A plan for the MI upgrades was presented. The major elements of this plan consist of an upgrade of a MI quad power supply, which is nearly complete, and the addition of two more RF stations. The cavities to be installed currently exist as spares so there is no design and prototyping required. Comment • The project has decided to build the DCCT in-house. The committee supports this effort since the technology and design of this device is well developed and well known. Recommendation • Work with Fermilab management to acquire resources needed to complete the accelerator and beamline modifications. Director's CD-2/3a Review of the MicroBooNE Project
Reviewer Write-ups • Write-up template (Review Closeout Presentation Format) is posted on Director’s Review Webpage. http://www.fnal.gov/directorate/OPMO/Projects/MBooNE/DirRev/2011/03_29/ Template-Closeout_Presentation_DR_MicroBooNE_2011-03-29.docx • Write-ups are to be sent to Terry Erickson at terickson@fnal.gov prior to 7:30 AM on Thursday, July 14 for the Closeout Dry Run starting at 8:30 AM • A final report will be issued within 1 weeks after the closeout. Director's CD-2/3a Review of the MicroBooNE Project
Questions and Answers Discussion Director's CD-2/3a Review of the MicroBooNE Project