Project Completion Report. Project Summary. Client: MTU Detroit Diesel Australia Contract No.: 1161873. Project Overview. The generator package formed part of the CSBP initiated NAAN3 project which aimed to increase production in their Kwinana facility.
E N D
Project Summary Client: MTU Detroit Diesel Australia Contract No.: 1161873
Project Overview • The generator package formed part of the CSBP initiated NAAN3 project which aimed to increase production in their Kwinana facility. • Aerison’s scope of supply included the following main components……… • Painted skid base with integral double skinned fuel tank (3500L) • Stainless steel acoustic enclosure • Inlet and outlet ventilation system • Removable roof • Roof mounted muffler • Fitting of free issue generator set and radiator to skid base • Full mechanical assembly of acoustic enclosure package
Project Overview • Parties Involved • Primary Stakeholder: CSBP • EPCM: MTU Detroit Diesel Australia • Supply Contractor: Aerison • Aerison’s Scope • Design, fabricate, assemble & transport to site…… • One off acoustic diesel generator package with integrated fuel tank
Design • Aerison • Similar to units previously supplied • Double skinned tank changed in regards to previous designs to • incorporate double skin at sides also • Stainless steel panels • Removable roof • Semrad fuel control system
Fabrication – In House • Base frame and tank • Structural frame work • Inlet ventilation system • Outlet ventilation system Base Frame
Fabrication – In House Structural Framework Inlet / Outlet Ventilation System
Fabrication – Sub Contractor • Stainless steel panels Cohesive • Stainless steel doors Cohesive • Flashing Cohesive • Muffler Universal • Weather louvreBradflow • Surface treatment RPC
Fabrication – Sub Contractor Insulation Fit Out Complete Panels Door Trial Assembly
Fabrication – Sub Contractor Muffler Elbow & Weather Cowl Weather Louvre
Project Pictures-Complete Assembly Outlet End Inlet End Fuel Connections Exhaust Duct & Blankets
Project Pictures-Complete Assembly Fuel Interface Genset Installation Genset Removable Roof
Project Pictures-Complete Assembly CSBP Generator Package
Project Summary Safety and Environment • Target – Nil Incident Actual – Nil Incident • Comments • Safety and environment record for project excellent • No reported incidents from sub contractors
Project Summary Scope of Works • Target - Original Contract Scope of Works Total Number of SCN’s 4 • Total Approved 3 • Comments • Project completed on time • $10,260 in variations
Project Summary Schedule
Project Summary Schedule • Original Contract Delivery 31/01/2013 Actual Practical Completion – March 2013 • (Contractual obligations fulfilled – Extension due to external client issues) • Comments • Schedule extremely tight from the beginning • A lot of initiative and assisting of client required to keep the project on track
Project Summary Budget and Margin
Project Summary Budget and Margin • Original Contract Sum $189,200 Expected Final $199,460 • Original Contract Margin $37,925 (20%) Expected Final $15,698 (8%) • Comments • Over budget items were:- • Drafting (-$11,408) • Management (-$20,017) • Fabrication Labour (-$7,315) • Assembly Labour • Under budget items were:- • Materials ($1,700) • Panels and Doors ($8,156) • Variations
Project Summary Quality • Target – Nil Quality Issues or NCR’s Actual – Nil • Comments • Internal fabrication checks • Sub contractor quality review documentation • Sub contractor external expections
Issues Budget • Comments • Drafting • - Significantly underestimated (~$9,000 estimated / ~$20,000 used) • Workshop hours • - Underestimated in regards to ventilation inlet/outlet system • - 370 hours used in total (290 allocated to work shop – Additional 80 hours • allocated due to shortfall with inlet/outlet ventilation system) • Assembly hours • - 140 hours estimated • - 80 additional hours used • ~ 45 hours covered by variation • ~ 10 hours caused by direct work shop error • Management and Engineering • - Significantly underestimated (~$18,000 estimated / ~$38,000 used)
Issues General • Subcontractors • - Subcontractors internal quality inspections poor • - Subcontractors external quality inspections not adequate • Drafting • - Missing detail led to additional work and time expended • Engineering • - Lack of consideration for a few assembly items (grid mesh / silencer • connection to radiator) • - Bolt take offs not efficient or correct • Management • - Greater control needed to be taken of design process at an earlier stage • - Due to the lack of document control and an organised process on the clients • side a lot of gentle persuasion and recording required to maintain forward • momentum of project while maintaining contractual obligations and cover.
Project Summary Human Resources • Comments • Expeditor – Good • - Expediting very good where required • QA – Internal Good / External Poor • - All internal issues identified and rectified in at work shop stage • - Muffler quality and panel quality documentation poor • Engineering – Good (Needs to flow more from the start) • Document Control – Restricted due to no client document control • Safety – Excellent • Management – Good • - Management was required to be very tight due to lack of budget in critical • areas
Project Summary Communications • Comments • Internal • Sub contractor • Client
Project Summary Client Satisfaction • Client and CSBP happy to date with final product – Commissioning and noise test yet to take place
Project Summary Lesson Learnt • Transport • Quality • Contract management • At source inspections
Project Summary Project Completion • Unfinished Business • Comments • Thank You Letter • Bank Guarantees • Future Business or Related Projects • Aerison Procedures