160 likes | 258 Views
Contract B Construction Activities. 10.22.2009. 5.20.2010. Norbeck Road Bridge. Contract B Construction Activities. N. 5.20.2010. 10.22.2009. Longmead Crossing Drive Bridge. 7.9.2010. Longmead Crossing Drive Bridge. Contract B Construction Activities. 10.22.2009. 5.20.2010.
E N D
Contract B Construction Activities 10.22.2009 5.20.2010 Norbeck Road Bridge
Contract B Construction Activities N 5.20.2010 10.22.2009 Longmead Crossing Drive Bridge
7.9.2010 Longmead Crossing Drive Bridge
Contract B Construction Activities 10.22.2009 5.20.2010 Layhill Road Bridge
Contract B Construction Activities 7.9.2010 Layhill Road Bridge
Contract B Construction Activities Pre-construction rendering 10.22.2009 5.20.2010 Northwest Branch Bridge west of Layhill Road
7.9.2010 Northwest Branch Bridge west of Layhill Road
Contract B Construction Activities 10.22.2009 5.20.2010 7.9.2010 Bridge over Northwest Branch and Bonifant Road
Contract B Construction Activities 10.22.2009 5.20.2010 New Hampshire Avenue Bridge
Contract B Construction Activities 7.9.2010 New Hampshire Avenue Bridge
Contract B Work As of June 2010 • Precast items: • Sound Barrier 761,700 SF 6% complete • Pipe 48" or smaller 55,000 LF 30% complete • Manholes and Inlets 500 Ea 24% complete • MSE Walls 64,000 SF 44% complete • 344 Girders 48,000 LF 43% complete Cast-in-place items: • Sound Barrier Footings 125,000 LF 13% complete • Bridge Decks 650,000 SF 11% complete • Parapets 22,000 LF 0% complete • Special Piers 62 Ea 58% complete • Total Concrete Placed 70,000 CY 32% complete Steel Girders: • 53 Girders 23,500 LF 19% complete (12,000,000 LBS) Paving items: • Hot Mix Asphalt (HMA) 460,000 TN 0% complete
Contract C: US 29 to I-95 Contract C Completion 100% 68.9% - $ 68.3% - Time $513.9M Contract Amount
Contract C Construction Activities 5.21.2009 5.20.2010 Old Columbia Pike Bridge
Contract C Construction Activities 7.9.2010 5.20.2010 Old Columbia Pike Bridge
Contract C Construction Activities Pre-construction rendering Aerial views of ICC construction at US 29 5.20.2010 10.22.2009 US 29 Interchange