An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Multidisciplinary Site Development and Clinical Care Working Group Report 28 July 2004

  2. ACCOMPLISHMENTS

  3. ACCOMPLISHMENTS OVER PAST YEAR • One urban site - 1 Military Hospital – is open and seeing on average 30 patients per day • One rural site – Mtubatuba Sickbay – is open and seeing on average 8 patients per day • Resources at two other sites – 2 Military Hospital and Umtata have been increased so that they should open within the next three months • Site PIs have begun to have weekly conference calls

  4. ACCOMPLISHMENTS OVER PAST YEAR • The format for Site Standard Operating Procedures has been established and 1 Mil, Mtubatuba and 2 Mil are well on their way to completing them: • Part I: Site Specific Procedures • clinic schedule, staff contact information, staff coverage policies, hospital admissions, etc. • Part II: Protocol Manual of Operations • Specific information for performing each protocol • Developed by DMCOC Regulatory Section • Part III: Phidisa Policies • Travel, cell phone, etc. • Part IV: Staff Position Descriptions

  5. ACCOMPLISHMENTS DURING THIS CONFERENCE Phidisa Site Governance:

  6. ACCOMPLISHMENTS DURING THIS CONFERENCE • Site Position Descriptions • Site Position Descriptions have been reviewed and approved by this group • Additional Site Position Descriptions are being written, and final drafts will be available on Thursday 29 July: • Social Worker • Psychologist • Dietician • Chaplain • Community Worker

  7. GOALS OVER NEXT YEAR

  8. OPEN FOUR REMAINING PHIDISA SITES • 2 Military to open 6 September 2004 • Umtata to open 4 October 2004 • Both sites will complete Phases 2 and 3 of “Development of New Phidisa Sites” guidelines (document to be submitted to EC) before these dates • Bloemfontein and Phalaborwa • Site PIs will communicate with Site Development Working Group and commence Phase 1 (Assessment of Current Site Status) of the “Development of New Phidisa Sites” by 1 November 2004 • Timelines for Phase 2 (Closing the Gap of Needs) and Phase 3 (Site Initiation and Program Roll out) will depend upon the needs found in the Phase 1 assessment

  9. OPEN FOUR REMAINING PHIDISA SITES • Rural Site Considerations • The group discussed the challenges of : • Clinical care related to study participants traveling from remote areas to rural study sites • Staff recruitment and retention at rural study sites • Study participant recruitment and retention at rural study sites • The group recognizes that DMCOC Deputy Director for Clinical Affairs is preparing a summary of options for the DMCOC Director to address these issues

  10. COMPLETE SOPs and PDs • SOPs • 1 Military, Mtubatuba and 2 Military will complete their SOPs by 1 September 2004 • Umtata will complete its SOPs prior to the Site Initiation Visit • Bloemfontein and Phalaborwa will begin their SOPs and complete them prior to the Site Initiation Visit • PDs: The group requests that: • All PDs be completed and submitted to the EC by 15 August; and that • The EC approve a final version of the PDs by 1 September so that they can be signed by all Phidisa personnel (particularly new personnel at 2 Mil and Umtata)

  11. INCREASE ENROLLMENT • Projected Enrollment over next year: * Once sites are open to enrollment

  12. IMPROVE COMMUNICATIONS: Phidisa Sites and SAMHS • Increase “buy-in” from appropriate SANDF infrastructure • 1-, 2- Mil an Bloemfontein to get service agreements with relevant services • All Site PIs to attend monthly meetings with their respective OICs, OCs and SO1 to update them on the progress and needs of the project • Rotate SAMHS doctors through Phidisa clinics • Each site will develop a structured teaching curriculum to educate rotating physicians on HIV, AIDS and clinical research • Each site will work to accredit the rotation for CPD points • Phidisa doctors and nurses will attend ward rounds • Each site will send a doctor and nurse to all inpatient rounds (Internal Medicine and Infectious Diseases) and – as possible – to other meetings such as journal clubs, departmental meetings

  13. IMPROVE COMMUNICATIONS: Phidisa Sites and DMCOC • The Working Group requests open, consistent and clear lines of communication between all sites and DMCOC: • An every two-week newsletter from DMCOC to all Phidisa staff summarizing all important events related to Phidisa, including: • Critical personnel changes (site and DMCOC) • Policy changes • Protocol progress • Access to EC meeting minutes, or relevant EC meeting outcomes (posted on website or emailed) • A current Phidisa personnel directory containing contact information (posted on website or emailed) • DMCOC SOPs outlining timelines for response to site queries, and next steps if timelines are not met • When requested, sites will provide the DMCOC Communication Section with site information in a timely fashion

  14. IMPROVE COMMUNICATIONS: Among Phidisa Sites/Role Groups (1) • Site Principal Investigators/Physicians: • Conference call • Every two weeks: 1st and 3rd Mondays at 1830 • Chair: DMCOC Chief Medical Officer • Participants: Site PIs and other physicians as necessary • Content: 30 minutes clinical issues, 30 minutes administrative • Site PI Conference • Every four months (to coincide with National HIV Clinicians meetings when possible) • Chair: Rotating among PIs • Participants: Site PIs, DMCOC Deputy Director for Clinical Operations, Chief Medical Officer, Medical Monitor and other physicians as necessary. • One meeting annually will be a joint Site PI and SC conference

  15. IMPROVE COMMUNICATIONS: Among Phidisa Sites/Role Groups (2) • Site Nurse Coordinators: • Conference call • Thursdays at 1400 • Chair: Starting with 1 Mil Site SC • Participants: Site SCs and other nurses as necessary • Content: clinical, administrative and protocol issues • Joint Site PI/SC Conference • Attend one joint site PI and SC conference annually • Chair: Rotating among PIs • Participants: Site PIs, Site Nurse Coordinator DMCOC Deputy Director for Clinical Operations, Chief Medical Officer, Medical Monitor and other physicians and nurses as necessary

  16. IMPROVE COMMUNICATIONS: Among Phidisa Sites/Role Groups (3) • Social Workers: • Conference call • Wednesdays at 1300 • Chair: Ms. Biyela • Participants: Social Workers • Content: relevant study participant issues • Other Site role groups to consider having conference calls if needed, but increased communication (email, telephone calls) will be promoted

  17. IMPROVE COMMUNICATIONS: Among Phidisa Sites/Role Groups (4) • The group requests that, at each annual Phidisa conference, time be allotted for site role group meetings • Each role group will submit an agenda to the DMCOC Deputy Director for Clinical Operations prior to the annual Phidisa conference

  18. IMPROVE COMMUNICATIONS: Within a Site • Each site will have, at minimum: • One weekly administrative/management meeting to include the Site PI, SC and Administrator • One weekly didactic meeting to train all clinical staff on aspects of HIV/AIDS, clinical research, internal medicine, etc. • One weekly interdisciplinary meeting to discuss patient issues

  19. RESOURCES AND BUDGETS

  20. Personnel Requirements ( )=current number in role

  21. Personnel Requirements ( )=current number in role

  22. Budgets • Each Site PI is working with the HJF Project Coordinator to produce annual budgets which will be submitted to the EC on Thursday 29 July